S.Amdt. 3406
What it does: Rewrites page 607, line 21 through “Not later than” on line 24What it changes
1 change to S. 2410
The Congressional Record cuts off the end of this amendment, so some changes may be missing.
Rewrites page 607, line 21 through “Not later than” on line 24
ReplacesPrinted pageRemoves page 607, line 21 through “Not later than” on line 24 of the printed bill. See that page
Inserted: SEC. 1625. SELECTION OF CONTRACTORS FOR EVOLVED EXPENDABLE LAUNCH VEHICLE PROGRAM.
Inserted: (a) Requirement to Consider Government-provided Competitive Advantage.--In evaluating any offers submitted to the Department of Defense in response to a solicitation for offers for the Evolved Expendable Launch Vehicle program (or any successor to that program), the Secretary of Defense shall consider any situation in which the cost of production or manufacturing operations, including systems and factory engineering, program management, standard integration and testing, launch and range activities, infrastructure, and parts obsolescence mitigation, or certification-related activities, is not fully borne by the offeror for such contract because of government-provided funds.
Inserted: (b) Report on Reliance of Evolved Expendable Launch Vehicle Program on Foreign Manufacturers.--Not later than
Original wording
On page 607, strike line 21 and all that follows through “Not later than” on line 24, and insert the following:
Read automatically from the Congressional Record. Check the original before relying on it.
As printed
SA 3406. Mrs. FEINSTEIN (for herself and Mrs. Boxer) submitted an amendment intended to be proposed by her to the bill S. 2410, to authorize appropriations for fiscal year 2015 for military activities of the Department of Defense, for military construction, and for defense activities of the Department of Energy, to prescribe military personnel strengths for such fiscal year, and for other purposes; which was ordered to lie on the table; as follows:
On page 607, strike line 21 and all that follows through “Not later than” on line 24, and insert the following:
SEC. 1625. SELECTION OF CONTRACTORS FOR EVOLVED EXPENDABLE LAUNCH VEHICLE PROGRAM.
(a) Requirement to Consider Government-provided Competitive Advantage.--In evaluating any offers submitted to the Department of Defense in response to a solicitation for offers for the Evolved Expendable Launch Vehicle program (or any successor to that program), the Secretary of Defense shall consider any situation in which the cost of production or manufacturing operations, including systems and factory engineering, program management, standard integration and testing, launch and range activities, infrastructure, and parts obsolescence mitigation, or certification-related activities, is not fully borne by the offeror for such contract because of government-provided funds.
(b) Report on Reliance of Evolved Expendable Launch Vehicle Program on Foreign Manufacturers.--Not later than
Legislative Activity
Stay on top of the latest movement without scrolling through every action
Senate amendment submitted
June 26, 2014