What it does: Strikes title I
Submitted May 8, 2013

What it changes

1 change to S. 601 · shown in the bill's text

Strikes a provision
  1. Strikes title I

    Strikes

    In S. 601 · Reported to Senate

    Struck: TITLE I--WATER RESOURCE PROJECTS

    Struck: SEC. 1001. PURPOSES.

    Struck: The purposes of this title are--

    Struck: (1) to authorize projects that--

    Show 36 more struck paragraphs

    Struck: (A) are the subject of a completed report of the Chief of Engineers containing a determination that the relevant project--

    Struck: (i) is in the Federal interest;

    Struck: (ii) results in benefits that exceed the costs of the project;

    Struck: (iii) is environmentally acceptable; and

    Struck: (iv) is technically feasible; and

    Struck: (B) have been recommended to Congress for authorization by the Assistant Secretary of the Army for Civil Works; and

    Struck: (2) to authorize the Secretary--

    Struck: (A) to review projects that require increased authorization; and

    Struck: (B) to request an increase of those authorizations after--

    Struck: (i) certifying that the increases are necessary; and

    Struck: (ii) submitting to Congress reports on the proposed increases.

    Struck: SEC. 1002. PROJECT AUTHORIZATIONS.

    Struck: The Secretary is authorized to carry out projects for water resources development, conservation, and other purposes, subject to the conditions that--

    Struck: (1) each project is carried out--

    Struck: (A) substantially in accordance with the plan for the project; and

    Struck: (B) subject to any conditions described in the report for the project; and

    Struck: (2) a Report of the Chief of Engineers has been completed and a referral by the Assistant Secretary of the Army for Civil Works has been made to Congress as of the date of enactment of this Act for the project.

    Struck: SEC. 1003. PROJECT REVIEW.

    Struck: (a) In General.--For a project that is authorized by Federal law as of the date of enactment of this Act, the Secretary may modify the authorized project cost set under section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280)--

    Struck: (1) by submitting the required certification and additional information to Congress in accordance with subsection (b); and

    Struck: (2) after receiving an appropriation of funds in accordance with subsection (b)(3)(B).

    Struck: (b) Requirements for Submission.--

    Struck: (1) Certification.--The certification to Congress under subsection (a) shall include a certification by the Secretary that--

    Struck: (A) expenditures above the authorized cost of the project are necessary to protect life and safety, maintain critical navigation routes, or restore ecosystems;

    Struck: (B) the project continues to provide benefits identified in the report of the Chief of Engineers for the project; and

    Struck: (C) for projects under construction--

    Struck: (i) a temporary stop or delay resulting from a failure to increase the authorized cost of the project will increase costs to the Federal Government; and

    Struck: (ii) the amount requested for the project in the budget of the President or included in a work plan for the expenditure of funds for the fiscal year during which the certification is submitted will exceed the authorized cost of the project.

    Struck: (2) Additional information.--The information provided to Congress about the project under subsection (a) shall include, at a minimum--

    Struck: (A) a comprehensive review of the project costs and reasons for exceeding the authorized limits set under section 902 of the Water Resources Development Act of 1986 (33 U.S.C. 2280);

    Struck: (B) an expedited analysis of the updated benefits and costs of the project; and

    Struck: (C) the new funding level needed to complete the project.

    Struck: (3) Approval of congress.--The Secretary may not change the authorized project costs under subsection (a) unless--

    Struck: (A) a certification and required information is submitted to Congress under subsection (b); and

    Struck: (B) after such submission, amounts are appropriated to initiate or continue construction of the project in an appropriations or other Act.

    Struck: (c) Termination of Effectiveness.--The authority of the Secretary under this section terminates on the date that is 3 years after the date of enactment of this Act.

    Original wording

    Strike title I.

Read automatically from the Congressional Record. Check the original before relying on it.

As printed

SA 817. Mr. SESSIONS submitted an amendment intended to be proposed by him to the bill S. 601, to provide for the conservation and development of water and related resources, to authorize the Secretary of the Army to construct various projects for improvements to rivers and harbors of the United States, and for other purposes; which was ordered to lie on the table; as follows:

Strike title I.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

Floor Latest Action

Senate amendment submitted

May 8, 2013