To extend the time required for construction of a hydroelectric project, and for other purposes.

Latest

One Hundred Ninth Congress of the United States of America

At the Second Session

Begun and held at the City of Washington on Tuesday, the third day of January, two thousand and six

H. R. 4377

AN ACT

To extend the time required for construction of a hydroelectric project, and for other purposes.

1.

Arrowrock hydroelectric project

Notwithstanding the time period specified in section 13 of the Federal Power Act (16 U.S.C. 806) that would otherwise apply to the Federal Energy Regulatory Commission project numbered 4656, on request of the licensee, the Commission shall—

(1)

if the license for the project is in effect on the date of the enactment of this Act, extend the period for commencing construction of project works for a period of 3 years beginning on the date of enactment of this Act; or

(2)

if the license for the project has been terminated before the date of enactment of this Act, reinstate the license and extend the period for commencing construction of project works for an additional 3-year period beginning on the date of enactment of this Act.

Speaker of the House of Representatives.

Vice President of the United States and President of the Senate.