II
109th CONGRESS
1st Session
S. 2099
IN THE SENATE OF THE UNITED STATES
December 14, 2005
Mr. Reid (for himself, Mr. Ensign, Mr. Bennett, and Mr. Hatch) introduced the following bill; which was read twice and referred to the Committee on Environment and Public Works
A BILL
To amend the Nuclear Waste Policy Act of 1982 to require commercial nuclear utilities to transfer spent nuclear fuel from spent nuclear fuel pools into spent nuclear fuel dry casks and convey to the Secretary of Energy title to all spent nuclear fuel thus safely stored.
Short title
This Act may be cited as
the Spent Nuclear Fuel On-Site Storage
Security Act of 2005
.
Dry Cask Storage of Spent Nuclear Fuel
In general
Title I of the Nuclear Waste Policy Act of 1982 (42 U.S.C. 10121 et seq.) is amended by adding at the end the following:
Dry Cask Storage of Spent Nuclear Fuel
Dry cask storage of spent nuclear fuel
Definitions
In this section:
Contractor
The term contractor means a person that holds a contract under section 302(a).
Spent nuclear fuel pool
The term spent nuclear fuel pool means a water-filled container in which spent nuclear fuel rods are stored.
Spent nuclear fuel dry cask
The term spent nuclear fuel dry cask means the container, and all the components and systems associated with the container, in which spent nuclear fuel is stored at a Commission-licensed independent spent fuel storage facility located at the power reactor site. The design of any such spent nuclear fuel dry cask shall be approved by the Commission.
Transfer of spent nuclear fuel
In general
A contractor shall transfer spent nuclear fuel from spent nuclear fuel pools to spent nuclear fuel dry casks at a Commission-licensed independent spent fuel storage facility located at the power reactor site.
Spent nuclear fuel stored as of date of enactment
A contractor shall complete the transfer of all spent nuclear fuel that is stored in spent nuclear fuel pools as of the date of enactment of this subsection not later than 6 years after the date of enactment of this subsection.
Spent nuclear fuel stored after date of enactment
A contractor shall complete the transfer of any spent nuclear fuel that is stored in a spent nuclear fuel pool after the date of enactment of this subsection not later than 6 years after the date on which the spent nuclear fuel is discharged from the reactor.
Inadequate funds
If funds are not available to complete a transfer under paragraph (2) or (3), the contractor may apply to the Commission to extend the deadline for the transfer to be completed.
Funding
The Secretary shall make grants to compensate a contractor for expenses incurred in carrying out subsection (b), including costs associated with—
licensing and construction of an independent spent fuel storage facility located at the power reactor site;
construction and delivery of spent nuclear fuel dry casks;
transfers of spent nuclear fuel;
documentation relating to the transfers;
security; and
hardening.
Conveyance of title
Determination
Not later than 30 days after the transfer of spent nuclear fuel from a spent nuclear fuel pool to a spent nuclear fuel dry cask, the Commission shall determine whether the contractor carried out the transfer in full compliance with regulations promulgated by the Commission.
Noncompliance
If the Commission determines that any technical standard or compliance provision under the regulations was not complied with, the Commission shall—
notify the contractor; and
take such actions as are necessary to obtain full compliance.
Certification and conveyance of title
When the Commission determines that the contractor has fully complied with the regulations—
the Commission shall certify that safe transfer has been accomplished; and
the Secretary shall accept the conveyance of title to the spent nuclear fuel dry cask (including the contents of the cask) from the contractor.
Responsibility
A conveyance of title under paragraph (3)(B) shall confer on the Secretary full responsibility (including financial responsibility) for the possession, stewardship, maintenance, and monitoring of all spent nuclear fuel transferred to the Secretary.
.
Funding
Section 302(d) of the Nuclear Waste Policy Act of 1982 (42 U.S.C. 10222(d)) is amended—
in paragraph (5),
by striking and
at the end;
in paragraph (6),
by striking the period at the end and inserting ; and
;
and
by adding at the end the following:
the provision of grants under section 185(d).
.
Immediate conveyance of title to spent nuclear fuel previously certified to be in compliance
Not later than 30 days after the date of enactment of this Act, the Secretary of Energy shall accept the conveyance of title to all spent nuclear fuel with respect to which, before the date of enactment of this Act, the Nuclear Regulatory Commission has certified that a contractor under section 302 of the Nuclear Waste Policy Act of 1982 (42 U.S.C. 10222) has completed transfer to spent nuclear fuel dry casks in compliance with applicable regulations in effect as of the date of transfer.