S. 2348Senate109th Congress (2005-2007)In Committee

Nuclear Release Notice Act of 2006

Introduced March 1, 2006

Legislative Activity

Stay on top of the latest movement without scrolling through every action

5 earlier actions
SenateCalendars Latest Action

Placed on Senate Legislative Calendar under General Orders. Calendar No. 637.

September 25, 2006

View full timeline
SenateIntro Referral

Introduced in Senate

March 1, 2006

SenateIntro Referral

Sponsor introductory remarks on measure. (CR S1581-1582)

March 1, 2006

SenateIntro Referral

Read twice and referred to the Committee on Environment and Public Works.

March 1, 2006

SenateCommittee

Committee on Environment and Public Works. Ordered to be reported with an amendment in the nature of a substitute favorably.

September 13, 2006

SenateCommittee

Committee on Environment and Public Works. Reported by Senator Inhofe with an amendment in the nature of a substitute. With written report No. 109-347. Additional views filed.

September 25, 2006

SenateCalendars

Placed on Senate Legislative Calendar under General Orders. Calendar No. 637.

September 25, 2006

Floor Debate

6 members

What members said about S. 2348 on the floor

2 Republicans4 Democrats
Susan M. Collins
Sen. Susan M. CollinsR-ME · Sep 13, 2006

Mr. President, I ask unanimous consent that the Committee on Banking, Housing, and Urban Affairs be authorized to meet during the session of the Senate on September 13, 2006, at 10 a.m., to conduct a…

Mark L. Pryor
Sen. Mark L. PryorD-AR · Mar 1, 2006

Mr. President, this week marks the 6-month anniversary of when Hurricane Katrina ravaged the gulf coast, destroying lives and dreams along the way. Thousands upon thousands of homes were also ruined,…

Barack Obama
Sen. Barack ObamaD-IL · Mar 1, 2006

Mr. President, less than 2 months ago, it was announced by Exelon Nuclear that an environmental monitoring program discovered higher than normal concentrations of tritium in the groundwater near the…

Barack Obama
Sen. Barack ObamaD-IL · Mar 1, 2006

Mr. President, less than 2 months ago, it was announced by Exelon Nuclear that an environmental monitoring program discovered higher than normal concentrations of tritium in the groundwater near the…

Kent Conrad
Sen. Kent ConradD-ND · Mar 1, 2006

Mr. President, today, I am reintroducing, with Senator Rockefeller, a bill to make some small but important changes to the Qualified Zone Academy Bond, QZAB, program. The QZAB program helps…

Show 2 more
Barbara Boxer
Sen. Barbara BoxerD-CA · Mar 1, 2006

Mr. President, I am pleased to introduce legislation today to double the funding for veterans mental health care over the next 5 years. Our brave veterans returning from Iraq and Afghanistan have…

Chuck Grassley
Sen. Chuck GrassleyR-IA · Mar 1, 2006

Mr. President, I ask unanimous consent that the text of a bill I introduced today that may be cited as the ``America's Business Choice Act'' be printed in the Record.

Bill Text

2 versions available

Reading Mode
Latest
Reported to SenateIssued September 25, 2006

II

Calendar No. 637

109th CONGRESS

2d Session

S. 2348

[Report No. 109–347]

IN THE SENATE OF THE UNITED STATES

March 1, 2006

Mr. Obama (for himself, Mr. Durbin, Mrs. Boxer, Mrs. Clinton, and Mr. Voinovich) introduced the following bill; which was read twice and referred to the Committee on Environment and Public Works

September 25, 2006

Reported by Mr. Inhofe, with an amendment

Strike out all after the enacting clause and insert the part printed in italic

A BILL

To amend the Atomic Energy Act of 1954 to require a licensee to notify the Atomic Energy Commission, and the State and county in which a facility is located, whenever there is an unplanned release of fission products in excess of allowable limits.

1.

Short title

This Act may be cited as the Nuclear Release Notice Act of 2006.

2.

Nuclear release notice requirement

Section 103 of the Atomic Energy Act of 1954 (42 U.S.C. 2133) is amended—

(1)

by redesignating subsection f. as subsection e.; and

(2)

in subsection e. (as so redesignated)—

(A)

by designating the first, second, and third sentences as paragraphs (1), (2), and (3), respectively;

(B)

by striking the subsection designation and paragraph (1) (as so designated) and inserting the following:

f.

Notice of unplanned release of radioactive substances

(1)

Notice required

(A)

In general

Each license issued for a utilization facility under this section or section 104 b. shall require as a condition of the license that in case of an unplanned release described in subparagraph (B), the licensee shall immediately notify the Commission, and the State and county in which the facility is located, of the release.

(B)

Unplanned releases

Subparagraph (A) applies to any unplanned release of quantities of fission products or other radioactive substances—

(i)

in excess of allowable limits for normal operation established by the Commission or other applicable Federal laws or standards; and

(ii)

within allowable limits for normal operation established by the Commission or other applicable Federal laws or standards but that occurs more than twice within a 2-year period originating from the same source, process, or equipment at a facility.

; and

(C)

in paragraph (3) (as so designated), by striking date of enactment of this subsection and inserting date of enactment of the Nuclear Release Notice Act of 2006.

1.

Short title

This Act may be cited as the Nuclear Release Notice Act of 2006.

2.

Nuclear release notice requirement

Section 103 of the Atomic Energy Act of 1954 (42 U.S.C. 2133) is amended by inserting after subsection d. the following:

e.

Notice of unplanned release of radioactive substances

(1)

Regulations

(A)

In general

Not later than 2 years after the date of enactment of the Nuclear Release Notice Act of 2006, the Commission shall promulgate regulations that require civilian nuclear power facilities licensed under this section or section 104(b) to provide notice of any release to the environment of quantities of fission products or other radioactive substances.

(B)

Considerations

In developing the regulations under subparagraph (A), the Commission shall consider requiring licensees of civilian nuclear power facilities to provide notice of the release—

(i)

not later than 24 hours after the release;

(ii)

to the Commission and the governments of the State and county in which the civilian nuclear power facility is located, if the unplanned release—

(I)
(aa)

exceeds allowable limits for normal operation established by the Commission; and

(bb)

is not subject to more stringent reporting requirements established in existing regulations of the Commission; or

(II)
(aa)

enters into the environment; and

(bb)

may cause drinking water sources to exceed a maximum contaminant level established by the Environmental Protection Agency for fission products or other radioactive substances under the Safe Drinking Water Act (42 U.S.C. 300f et seq.); and

(iii)

to the governments of the State and county in which the civilian nuclear power facility is located if the unplanned release reaches the environment by a path otherwise not allowed or recognized by the operating license of the civilian nuclear power facility and falls within the allowable limits specified in clause (ii), including—

(I)

considering any recommendations issued by the Liquid Radioactive Release Lessons-Learned Task Force;

(II)

the frequency and form of the notice; and

(III)

the threshold, volume, and radiation content that trigger the notice.

(2)

Effect

Nothing in this subsection provides to any State or county that receives a notice under this subsection regulatory jurisdiction over a licensee of a civilian nuclear power facility.

.

September 25, 2006

Reported with an amendment