Madam Speaker, pursuant to the Republican Leadership standards on earmarks, I am submitting the following information regarding earmarks I received as part of H.R. 2487, the Fiscal Year 2010 Commerce, Justice, Science, and Related Agencies…
Madam Speaker, pursuant to the Republican Leadership standards on earmarks, I am submitting the following information regarding earmarks I received as part of H.R. 2487, the Fiscal Year 2010 Commerce, Justice, Science, and Related Agencies Appropriations Act.
(1) $500,000 for the Region 43, Pierce County Metropolitan Public Safety Communications Interoperable First Responder Emergency Communication System
Requesting Entity: Pierce County Sheriff Department, 930 Tacoma Avenue, Tacoma, WA 98402
Agency: Department of Justice
Account: COPS Tech
Funding Requested by: Rep. Dave Reichert
Currently, Pierce County has several disparate radio systems which do not allow easy interoperability, or only provide minimal interoperability. There is a drastic need for improved operable communications and interoperable communications in Pierce County which will take advantage of new technology.
Two critical components of this project involve a county-wide radio system and 911 dispatch centers. Pierce County will plan, purchase and build a county-wide interoperable radio communications system and two 911 dispatch centers (one police and one fire communications facilities), co-locating participating PSAPs into physically separate, fully redundant and survivable Fire and Police communications facilities. This project will solve the County's interoperability issues and establish the capacity to use operating funds, staff and equipment more efficiently.
Building a regional interoperable communications system with two consolidated PSAPs will dramatically improve the ability of first responders to respond to natural or manmade disasters within Pierce County and improve day-to-day operational capabilities. This project comes at a critical time due to sun-setting technology and FCC mandates. Additionally, this will enable all first responders to become interoperable. Citizens of Pierce County and the Puget Sound will benefit from first responders rapidly deploying to events and communicating effectively for life safety issues.
Additionally, an estimated 1,080 prevailing wage jobs will be created to construct facilities and communications sites. Further, in-state companies will have the opportunity to participate in supplying building materials, equipment, supplies and services. Local and state governments will benefit from sales tax revenues and permitting fees.
Finance Plan:
------------------------------------------------------------------------ ------------------------------------------------------------------------ Site development:
Backhoe Excavation for Shelter Foundation Designs... 6,000
Shelter Foundation 12 x 32.......................... 18,500
Generator Foundation................................ 12,300
Fuel Tank Foundation................................ 10,200
Shelter, Fuel Tank and Generator Placement.......... 17,000
Utility Locate...................................... 1,100
High voltage electrical installation................ 30,000
Grounding for new shelter, generator, and tower 17,000
components.........................................
Tower Ice Bridge.................................... 5,000
Design Construction Drawings........................ 5,000
As Built Construction Drawings...................... 1,650
Shelter, Generator and Tank and Tower Foundation 5,000
design.............................................
Misc. Civil Construction (Includes extended Utility 21,200
Trenching, Rock/Site Finish, Landscaping, Misc.
Concrete and Bollards, Fuel Tank, install and fuel)
Site Acquisition and Zoning Services (Includes 3,100
Building Permit Processing, Zoning submittal and
Approval Process)..................................
General Testing (Includes Soil Resistivity Test, 8,000
Compact Test, Concrete Test, Grounding Test,
Generator Load Test, and Special Inspections)......
Construction Mgmt Services (includes Subcontractor's 26,100
Construction Management, Project management Project
Coordinator, Mobilization, Temp Facilities,
Transportation of materials to Site and Close out
Preparation).......................................
Tower Foundation.................................... 95,000
Crane Rental........................................ 15,000
Site Topographical Survey........................... 4,100
Standard Geotechnical Investigation................. 20,000
Tower Freight....................................... 18,500
Shelter Freight..................................... 31,000
Tower............................................... 98,000
12 x 32 Shelter w/aggregate ext. & twin A/C units... 94,000
Tower Lighting...................................... 11,000
Self-Supporting Tower Erection...................... 60,000
Fences/Gates........................................ 25,000
Building Permit review.............................. 3,000
Geotech............................................. 6,500
Site Drawings....................................... 2,000
Geotech Follow Up................................... 2,000
Radio base stations (Includes antenna combiners, 165,000
antennas, feedlines and lightning suppression......
Microwave backhaul equipment........................ 140,000
Multiplexers........................................ 20,000
Misc. Parts and Supplies............................ 2,750