An amendment numbered 14 printed in Part A of House Report 115-711 to require the Secretary to conduct a study of the status of the project for flood damage reduction and environmental restoration for the Muddy River authorized by WRDA 2000. The Secretary is required to submit a report to Congress describing the study and reasons for deauthorizing the project.
What it does: Adds SEC. ___. SENSE OF CONGRESS at the end of title IWhat it changes
1 change to H.R. 8
We couldn't match these changes to the text of H.R. 8, so they're shown as written.
Adds SEC. ___. SENSE OF CONGRESS at the end of title I
Adds a sectionInserted: SEC. ___. SENSE OF CONGRESS.
Inserted: It is the sense of Congress that the construction of a new lock at the Soo Locks at Sault Ste. Marie, Michigan, is vital to our national economy, national security, and national need for new critical infrastructure.
Original wording
At the end of title I, add the following:
Read automatically from the Congressional Record. Check the original before relying on it.
As printed
At the end of title I, add the following:
SEC. ___. SENSE OF CONGRESS.
It is the sense of Congress that the construction of a new lock at the Soo Locks at Sault Ste. Marie, Michigan, is vital to our national economy, national security, and national need for new critical infrastructure.
Legislative Activity
Stay on top of the latest movement without scrolling through every action
House amendment offered
June 6, 2018
View full timeline
House amendment offered
June 6, 2018
House amendment offered/reported by: Amendment (A014) offered by Mr. Nolan.(consideration: CR H4820-4821; text: CR H4820)
June 6, 2018 • 4:10 PM
House amendment agreed to: On agreeing to the Nolan amendment (A014) Agreed to by voice vote.
June 6, 2018 • 4:12 PM
Amendment agreed to Committee of the Whole
June 6, 2018 • 4:12 PM
Amendment (A014) offered by Mr. Nolan. (consideration: CR H4820-4821; text: CR H4820)
June 6, 2018 • 4:10 PM
On agreeing to the Nolan amendment (A014) Agreed to by voice vote.
June 6, 2018 • 4:12 PM