S.Amdt. 1373
What it does: Adds SEC. 12__. COMMUNITY SOLAR at the end of subtitle B of title IWhat it changes
1 change to S. 2657
Adds SEC. 12__. COMMUNITY SOLAR at the end of subtitle B of title I
Adds a sectionInserted: SEC. 12__. COMMUNITY SOLAR.
Inserted: (a) Community Solar Consumer Choice Program; Federal Government Participation in Community Solar.--
Inserted: (1) Definitions.--In this subsection:
Inserted: (A) Community solar.--The term "community solar" means a solar power plant, the benefits of the electricity produced by which are shared by 2 or more electricity customers.
Inserted: (B) Subscriber.--The term "subscriber" means an electricity customer who receives a benefit associated with the proportional output of the community solar facility of the customer.
Inserted: (2) Establishment of community solar consumer choice program.--
Inserted: (A) In general.--Not later than 1 year after the date of enactment of this Act, the Secretary shall establish a program to expand community solar options to--
Inserted: (i) individuals, particularly individuals that do not have regular access to onsite solar, including low- and moderate-income individuals;
Inserted: (ii) businesses;
Inserted: (iii) nonprofit organizations; and
Inserted: (iv) States and local and Tribal governments.
Inserted: (B) Alignment with existing Federal programs.--The Secretary shall align the program under subparagraph (A) with existing Federal programs that serve low-income communities.
Show 39 more inserted paragraphsShow less
Inserted: (C) Assistance to State and local governments.--In carrying out the program under subparagraph (A), the Secretary shall--
Inserted: (i) provide technical assistance to States and local and Tribal governments for projects to increase community solar;
Inserted: (ii) assist States and local and Tribal governments in the development of new and innovative financial and business models that leverage competition in the marketplace in order to serve community solar subscribers; and
Inserted: (iii) use National Laboratories to collect and disseminate data to assist private entities in the financing of, subscription to, and operation of community solar projects.
Inserted: (3) Federal government participation in community solar.--The Secretary shall expand the existing grant, loan, and financing programs of the Department to include community solar projects.
Inserted: (b) Establishment of Community Solar Programs.--
Inserted: (1) In general.--Section 111(d) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621(d)) is amended by adding at the end the following:
Inserted: "(20) Community solar programs.--
Inserted: "(A) Definitions.--In this paragraph:
Inserted: "(i) Community solar facility.--The term 'community solar facility' means a solar photovoltaic system that--
Inserted: "(I) allocates electricity to multiple electric consumers of an electric utility; and
Inserted: "(II) is--
Inserted: "(aa) connected to a local distribution facility of the electric utility;
Inserted: "(bb) located on or off the property of an electric consumer; and
Inserted: "(cc) owned by an electric utility, an electric consumer, or a third party.
Inserted: "(ii) Community solar program.--The term 'community solar program' means a service provided by an electric utility to an electric consumer served by the electric utility through which the value of electric energy generated by a community solar facility may be used to offset charges billed to the electric consumer by the electric utility.
Inserted: "(B) Standard.--Each electric utility shall offer a community solar program.".
Inserted: (2) Compliance.--
Inserted: (A) Time limitations.--Section 112(b) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622(b)) is amended by adding at the end the following:
Inserted: "(7)(A) Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 111, or set a hearing date for consideration, with respect to the standard established by paragraph (20) of section 111(d).
Inserted: "(B) Not later than 2 years after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 111 with respect to the standard established by paragraph (20) of section 111(d).".
Inserted: (B) Failure to comply.--
Inserted: (i) In general.--Section 112(c) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622(c)) is amended--
Inserted: (I) by striking "such paragraph (14)" and all that follows through "paragraphs (16)" and inserting "such paragraph (14). In the case of the standard established by paragraph (15) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (15). In the case of the standards established by paragraphs (16)"; and
Inserted: (II) by adding at the end the following: "In the case of the standard established by paragraph (20) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (20).".
Inserted: (ii) Technical correction.--
Inserted: (I) In general.--Section 1254(b) of the Energy Policy Act of 2005 (Public Law 109-58; 119 Stat. 971) is amended--
Inserted: (aa) by striking paragraph (2); and
Inserted: (bb) by redesignating paragraph (3) as paragraph (2).
Inserted: (II) Treatment.--The amendment made by paragraph (2) of section 1254(b) of the Energy Policy Act of 2005 (Public Law 109-58; 119 Stat. 971) (as in effect on the day before the date of enactment of this Act) is void, and section 112(d) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622(d)) shall be in effect as if those amendments had not been enacted.
Inserted: (C) Prior state actions.--
Inserted: (i) In general.--Section 112 of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622) is amended by adding at the end the following:
Inserted: "(g) Prior State Actions.--Subsections (b) and (c) shall not apply to the standard established by paragraph (20) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection--
Inserted: "(1) the State has implemented for the electric utility the standard (or a comparable standard);
Inserted: "(2) the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or
Inserted: "(3) the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility.".
Inserted: (ii) Cross-reference.--Section 124 of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2634) is amended by adding at the end the following: "In the case of the standard established by paragraph (20) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (20).".
Inserted: (c) Federal Contracts for Public Utility Services.--Section 501(b)(1) of title 40, United States Code, is amended by striking subparagraph (B) and inserting the following:
Inserted: "(B) Public utility contracts.--A contract under this paragraph for public utility services may be for a period of not more than 20 years.".
Original wording
At the end of subtitle B of title I, add the following:
Read automatically from the Congressional Record. Check the original before relying on it.
As printed
SA 1373. Mr. BENNET submitted an amendment intended to be proposed by him to the bill S. 2657, to support innovation in advanced geothermal research and development, and for other purposes; which was ordered to lie on the table; as follows:
At the end of subtitle B of title I, add the following:
SEC. 12__. COMMUNITY SOLAR.
(a) Community Solar Consumer Choice Program; Federal Government Participation in Community Solar.--
(1) Definitions.--In this subsection:
(A) Community solar.--The term “community solar” means a solar power plant, the benefits of the electricity produced by which are shared by 2 or more electricity customers.
(B) Subscriber.--The term “subscriber” means an electricity customer who receives a benefit associated with the proportional output of the community solar facility of the customer.
(2) Establishment of community solar consumer choice program.--
(A) In general.--Not later than 1 year after the date of enactment of this Act, the Secretary shall establish a program to expand community solar options to--
(i) individuals, particularly individuals that do not have regular access to onsite solar, including low- and moderate-income individuals;
(ii) businesses;
(iii) nonprofit organizations; and
(iv) States and local and Tribal governments.
(B) Alignment with existing Federal programs.--The Secretary shall align the program under subparagraph (A) with existing Federal programs that serve low-income communities.
(C) Assistance to State and local governments.--In carrying out the program under subparagraph (A), the Secretary shall--
(i) provide technical assistance to States and local and Tribal governments for projects to increase community solar;
(ii) assist States and local and Tribal governments in the development of new and innovative financial and business models that leverage competition in the marketplace in order to serve community solar subscribers; and
(iii) use National Laboratories to collect and disseminate data to assist private entities in the financing of, subscription to, and operation of community solar projects.
(3) Federal government participation in community solar.--The Secretary shall expand the existing grant, loan, and financing programs of the Department to include community solar projects.
(b) Establishment of Community Solar Programs.--
(1) In general.--Section 111(d) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2621(d)) is amended by adding at the end the following:
“(20) Community solar programs.--
“(A) Definitions.--In this paragraph:
“(i) Community solar facility.--The term ‘community solar facility' means a solar photovoltaic system that--
“(I) allocates electricity to multiple electric consumers of an electric utility; and
“(II) is--
“(aa) connected to a local distribution facility of the electric utility;
“(bb) located on or off the property of an electric consumer; and
“(cc) owned by an electric utility, an electric consumer, or a third party.
“(ii) Community solar program.--The term ‘community solar program' means a service provided by an electric utility to an electric consumer served by the electric utility through which the value of electric energy generated by a community solar facility may be used to offset charges billed to the electric consumer by the electric utility.
“(B) Standard.--Each electric utility shall offer a community solar program.”.
(2) Compliance.--
(A) Time limitations.--Section 112(b) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622(b)) is amended by adding at the end the following:
“(7)(A) Not later than 1 year after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority) and each nonregulated utility shall commence consideration under section 111, or set a hearing date for consideration, with respect to the standard established by paragraph (20) of section 111(d).
“(B) Not later than 2 years after the date of enactment of this paragraph, each State regulatory authority (with respect to each electric utility for which the State has ratemaking authority), and each nonregulated electric utility shall complete the consideration and make the determination under section 111 with respect to the standard established by paragraph (20) of section 111(d).”.
(B) Failure to comply.--
(i) In general.--Section 112(c) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622(c)) is amended--
(I) by striking “such paragraph (14)” and all that follows through “paragraphs (16)” and inserting “such paragraph (14). In the case of the standard established by paragraph (15) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (15). In the case of the standards established by paragraphs (16)”; and
(II) by adding at the end the following: “In the case of the standard established by paragraph (20) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (20).”.
(ii) Technical correction.--
(I) In general.--Section 1254(b) of the Energy Policy Act of 2005 (Public Law 109-58; 119 Stat. 971) is amended--
(aa) by striking paragraph (2); and
(bb) by redesignating paragraph (3) as paragraph (2).
(II) Treatment.--The amendment made by paragraph (2) of section 1254(b) of the Energy Policy Act of 2005 (Public Law 109-58; 119 Stat. 971) (as in effect on the day before the date of enactment of this Act) is void, and section 112(d) of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622(d)) shall be in effect as if those amendments had not been enacted.
(C) Prior state actions.--
(i) In general.--Section 112 of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2622) is amended by adding at the end the following:
“(g) Prior State Actions.--Subsections (b) and (c) shall not apply to the standard established by paragraph (20) of section 111(d) in the case of any electric utility in a State if, before the date of enactment of this subsection--
“(1) the State has implemented for the electric utility the standard (or a comparable standard);
“(2) the State regulatory authority for the State or the relevant nonregulated electric utility has conducted a proceeding to consider implementation of the standard (or a comparable standard) for the electric utility; or
“(3) the State legislature has voted on the implementation of the standard (or a comparable standard) for the electric utility.”.
(ii) Cross-reference.--Section 124 of the Public Utility Regulatory Policies Act of 1978 (16 U.S.C. 2634) is amended by adding at the end the following: “In the case of the standard established by paragraph (20) of section 111(d), the reference contained in this subsection to the date of enactment of this Act shall be deemed to be a reference to the date of enactment of that paragraph (20).”.
(c) Federal Contracts for Public Utility Services.--Section 501(b)(1) of title 40, United States Code, is amended by striking subparagraph (B) and inserting the following:
“(B) Public utility contracts.--A contract under this paragraph for public utility services may be for a period of not more than 20 years.”.
Legislative Activity
Stay on top of the latest movement without scrolling through every action
Senate amendment submitted
March 3, 2020