S.Amdt. 1404
What it does: Adds SEC. 18____. ACTION ON APPLICATIONS TO EXPORT NATURAL GAS at the end of subtitle H of title IWhat it changes
1 change to S. 2657
Adds SEC. 18____. ACTION ON APPLICATIONS TO EXPORT NATURAL GAS at the end of subtitle H of title I
Adds a sectionInserted: SEC. 18____. ACTION ON APPLICATIONS TO EXPORT NATURAL GAS.
Inserted: (a) Decision Deadline.--For proposals that must also obtain authorization from the Federal Energy Regulatory Commission or the United States Maritime Administration to site, construct, expand, or operate liquefied natural gas export facilities, the Secretary shall issue a final decision on any application for the authorization to export natural gas under section 3(a) of the Natural Gas Act (15 U.S.C. 717b(a)) not later than 45 days after the later of--
Inserted: (1) the conclusion of the review to site, construct, expand, or operate the liquefied natural gas export facilities required by the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and
Inserted: (2) the date of enactment of this Act.
Inserted: (b) Conclusion of Review.--For purposes of subsection (a), review required by the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) shall be considered concluded when the lead agency--
Inserted: (1) for a project requiring an Environmental Impact Statement, publishes a Final Environmental Impact Statement;
Inserted: (2) for a project for which an Environmental Assessment has been prepared, publishes a Finding of No Significant Impact; or
Inserted: (3) determines that an application is eligible for a categorical exclusion pursuant to National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) implementing regulations.
Inserted: (c) Judicial Action.--
Inserted: (1) Jurisdiction.--The United States Court of Appeals for the District of Columbia Circuit or the circuit in which the liquefied natural gas export facility will be located pursuant to an application described in subsection (a) shall have original and exclusive jurisdiction over any civil action for the review of--
Inserted: (A) an order issued by the Secretary with respect to the application; or
Inserted: (B) the failure of the Secretary to issue a final decision on the application.
Show 5 more inserted paragraphsShow less
Inserted: (2) Order to issue decision.--If the Court in a civil action described in paragraph (1) finds that the Secretary has failed to issue a decision on the application as required under subsection (a), the Court shall order the Secretary to issue the decision not later than 30 days after the order of the Court.
Inserted: (3) Expedited consideration.--The Court shall set any civil action brought under this subsection for expedited consideration and shall set the matter on the docket as soon as practical after the filing date of the initial pleading.
Inserted: (4) Appeals.--In the case of an application described in subsection (a) for which a petition for review has been filed--
Inserted: (A) upon motion by an applicant, the matter shall be transferred to the United States Court of Appeals for the District of Columbia Circuit or the circuit in which a liquefied natural gas export facility will be located pursuant to an application described in section 3(a) of the Natural Gas Act (15 U.S.C. 717b(a)); and
Inserted: (B) the provisions of this section shall apply.
Original wording
At the end of subtitle H of title I, add the following:
Read automatically from the Congressional Record. Check the original before relying on it.
As printed
SA 1404. Mr. BARRASSO (for himself and Mr. Cramer) submitted an amendment intended to be proposed by him to the bill S. 2657, to support innovation in advanced geothermal research and development, and for other purposes; which was ordered to lie on the table; as follows:
At the end of subtitle H of title I, add the following:
SEC. 18____. ACTION ON APPLICATIONS TO EXPORT NATURAL GAS.
(a) Decision Deadline.--For proposals that must also obtain authorization from the Federal Energy Regulatory Commission or the United States Maritime Administration to site, construct, expand, or operate liquefied natural gas export facilities, the Secretary shall issue a final decision on any application for the authorization to export natural gas under section 3(a) of the Natural Gas Act (15 U.S.C. 717b(a)) not later than 45 days after the later of--
(1) the conclusion of the review to site, construct, expand, or operate the liquefied natural gas export facilities required by the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.); and
(2) the date of enactment of this Act.
(b) Conclusion of Review.--For purposes of subsection (a), review required by the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) shall be considered concluded when the lead agency--
(1) for a project requiring an Environmental Impact Statement, publishes a Final Environmental Impact Statement;
(2) for a project for which an Environmental Assessment has been prepared, publishes a Finding of No Significant Impact; or
(3) determines that an application is eligible for a categorical exclusion pursuant to National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) implementing regulations.
(c) Judicial Action.--
(1) Jurisdiction.--The United States Court of Appeals for the District of Columbia Circuit or the circuit in which the liquefied natural gas export facility will be located pursuant to an application described in subsection (a) shall have original and exclusive jurisdiction over any civil action for the review of--
(A) an order issued by the Secretary with respect to the application; or
(B) the failure of the Secretary to issue a final decision on the application.
(2) Order to issue decision.--If the Court in a civil action described in paragraph (1) finds that the Secretary has failed to issue a decision on the application as required under subsection (a), the Court shall order the Secretary to issue the decision not later than 30 days after the order of the Court.
(3) Expedited consideration.--The Court shall set any civil action brought under this subsection for expedited consideration and shall set the matter on the docket as soon as practical after the filing date of the initial pleading.
(4) Appeals.--In the case of an application described in subsection (a) for which a petition for review has been filed--
(A) upon motion by an applicant, the matter shall be transferred to the United States Court of Appeals for the District of Columbia Circuit or the circuit in which a liquefied natural gas export facility will be located pursuant to an application described in section 3(a) of the Natural Gas Act (15 U.S.C. 717b(a)); and
(B) the provisions of this section shall apply.