S. 1008Senate110th Congress (2007-2009)In Committee

A bill to amend the Atomic Energy Act of 1954 to improve and strengthen the safety inspection process of nuclear facilities.

Introduced March 28, 2007

Legislative Activity

Stay on top of the latest movement without scrolling through every action

2 earlier actions
SenateIntro Referral Latest Action

Read twice and referred to the Committee on Environment and Public Works. (text of measure as introduced: CR S4055)

March 28, 2007

View full timeline
SenateIntro Referral

Introduced in Senate

March 28, 2007

SenateIntro Referral

Sponsor introductory remarks on measure. (CR S4054-4055)

March 28, 2007

SenateIntro Referral

Read twice and referred to the Committee on Environment and Public Works. (text of measure as introduced: CR S4055)

March 28, 2007

Floor Debate

10 members

What members said about S. 1008 on the floor

5 Republicans4 Democrats1 Independent
John F. Kerry
Sen. John F. KerryD-MA · Mar 28, 2007

Mr. President, I rise today with my colleague Senator Hagel, the Senator from Nebraska, to introduce the Military Reservist and Veteran Small Business Reauthorization Act of 2007. There are currently…

Michael B. Enzi
Sen. Michael B. EnziR-WY · Mar 28, 2007

Mr. President, Wyoming's late, great country music star Chris LeDoux has a song Some Things Never Change. I wish that were the case for Wyoming's hardworking livestock producers. As production…

Richard G. Lugar
Sen. Richard G. LugarR-IN · Mar 28, 2007

Mr. President, I rise to introduce the ``United States Brazil Energy Cooperation Pact.'' This bill would direct the Secretary of State to work with the Government of Brazil and other foreign…

Richard J. Durbin
Sen. Richard J. DurbinD-IL · Mar 28, 2007

Mr. President, today, Senator Hagel and I introduced the bipartisan Global Climate Change Security Oversight Act. We were joined by Senator Feinstein. Our bill states that the consequences of global…

Joseph R. Biden Jr.
Sen. Joseph R. Biden Jr.D-DE · Mar 28, 2007

Mr. President, for nearly 35 years I've been working on this floor to address the all too real public health and safety issues associated with drug and alcohol addiction. Stiff prosecution of…

Show 6 more
Mel Martinez
Sen. Mel MartinezR-FL · Mar 28, 2007

Mr. President, I am here to discuss a topic of great meaning to American families: educating our children. We all want what is best for our children, and to provide them with the tools they need to…

Chuck Hagel
Sen. Chuck HagelR-NE · Mar 28, 2007

Mr. President. I rise today to join Senator Durbin in introducing the Global Climate Change Security Oversight Act. Global climate change has implications beyond economic, environmental and energy…

John D. Rockefeller IV
Sen. John D. Rockefeller IVD-WV · Mar 28, 2007

Mr. President, I rise today to join my distinguished colleague, Senator Thad Cochran, in sponsoring the reauthorization of the National Writing Project. We have worked together for many years on the…

Bernard Sanders
Sen. Bernard SandersI-VT · Mar 28, 2007

Mr. President, today I am introducing legislation that would provide greater assurance to the citizens of our Nation that their elected officials will do everything within their power to provide the…

Bernard Sanders
Sen. Bernard SandersI-VT · Mar 28, 2007

Mr. President, today I am introducing legislation that would provide greater assurance to the citizens of our Nation that their elected officials will do everything within their power to provide the…

Thad Cochran
Sen. Thad CochranR-MS · Mar 28, 2007

Mr. President, today I am joined by my distinguished colleague and friend from West Virginia, Mr. Rockefeller, in introducing the National Writing Project Act of 2007. The National Writing Project…

Bill Text

Latest available legislative text

Reading Mode
Latest
Introduced in SenateIssued March 28, 2007

II

110th CONGRESS

1st Session

S. 1008

IN THE SENATE OF THE UNITED STATES

March 28, 2007

Mr. Sanders introduced the following bill; which was read twice and referred to the Committee on Environment and Public Works

A BILL

To amend the Atomic Energy Act of 1954 to improve and strengthen the safety inspection process of nuclear facilities.

1.

Independent safety assessments

Section 103 of the Atomic Energy Act of 1954 (42 U.S.C. 2133) is amended by inserting after subsection d. the following:

e.

Independent safety assessments

(1)

Development of procedure

Not later than 90 days after the date of enactment of this subsection, the Nuclear Regulatory Commission (referred to in this subsection as the Commission) shall develop an independent safety assessment procedure.

(2)

Conduct of assessment

(A)

Definition of eligible requestor

In this paragraph, the term eligible requestor means—

(i)

a Governor of a State in which a facility of a licensee is located;

(ii)

a public utility commission of a State in which a facility of a licensee is located; and

(iii)

a Governor of a State that—

(I)

because of dangers to the public relating to potential ingestion of water or foods that have been contaminated with radiation from a commercial nuclear power plant, is located in an emergency planning zone, as defined in section 350.2 of title 44, Code of Federal Regulations (or a successor regulation); and

(II)

is not the same State in which the facility of the licensee is located.

(B)

Request of assessment

(i)

In general

At the request of an eligible requestor, the Commission shall conduct an independent safety assessment in accordance with the independent safety assessment procedure developed under paragraph (1) if the licensee has—

(I)

applied to the Commission for—

(aa)

an extension of the operating license of the licensee; or

(bb)

approval of an extended power uprate for the licensee; or

(II)

during any 5-year period, received, under the reactor oversight process of the Commission, 2 or more greater-than-green inspection findings.

(ii)

Conduct of assessment

The Commission shall conduct an assessment requested by an eligible requestor under clause (i) not later than 18 months after the date on which the eligible requestor requested the assessment.

(3)

Inspection of facility

(A)

In general

In conducting an independent safety assessment under paragraph (2)(B), the Commission shall inspect the design, construction, maintenance, and operational safety performance of the facility of the licensee.

(B)

Scope of inspection

An inspection of a facility of a licensee conducted under subparagraph (A) shall—

(i)

be at least equal in scope, depth, and breadth to the independent safety assessment conducted in 1996 by the Commission of the Maine Yankee Nuclear Power Plant, located in Wiscasset, Maine; and

(ii)

include an examination of the systems of the facility of the licensee, including—

(I)

the reactor containment systems;

(II)

the reactor emergency core cooling systems;

(III)

the control room and containment ventilation systems;

(IV)

the electrical system (including testing of relevant transients);

(V)

the condensate and feedwater systems;

(VI)

the spent fuel storage systems;

(VII)

any other system requested by the Governor of the State, or a public utility commission of the State, in which the facility of the licensee is located; and

(VIII)

any other system identified by a majority of the members of an inspection team described in paragraph (4).

(4)

Inspection teams

(A)

In general

An independent safety assessment conducted under paragraph (2)(B) shall be conducted by an inspection team.

(B)

Composition

An inspection team shall be composed of not less than 25 members, of whom—

(i)

not less than 16 members shall be—

(I)

employees of the Commission; and

(II)

unaffiliated with the regional office of the Commission in the region in which the facility of the licensee is located;

(ii)

not less than 6 members shall be independent contractors who have not worked for, or at—

(I)

the facility of the licensee; or

(II)

any other nuclear power plant owned or operated by the owner or operator of the facility of the licensee; and

(iii)

not less than 3 members shall be appointed by the eligible requestor.

(5)

Report

(A)

Preparation of preliminary report

Not later than 90 days after the date on which an inspection team completes an independent safety assessment of a facility of a licensee under paragraph (2)(B), the inspection team shall prepare a preliminary report describing the findings and recommendations of the inspection team.

(B)

Availability of preliminary report

For a period of 90 days beginning on the date on which the inspection team completes a preliminary report prepared under subparagraph (A), the inspection team shall make available for review and comment by the public a copy of the preliminary report.

(C)

Consideration of comments

In preparing a final version of a preliminary report developed under subparagraph (A), the inspection team shall take into consideration any comments received from the public that are appropriate, as determined by the inspection team.

(D)

Submission of final version

Not later than 90 days after the date on which the period of review and public comment ends under subparagraph (B), the inspection team shall submit to the Commission a final version of the preliminary report developed under subparagraph (A).

(6)

Affect on licensing actions

A final decision by the Commission of whether to extend an operating license, approve an extended power uprate, or continue to operate under a license at a facility of a licensee assessed under paragraph (2)(B) shall not be made until the later of the date on which—

(A)

the Commission has completed the independent safety assessment of the facility of the licensee; and

(B)

the licensee has fully accepted and implemented each finding and recommendation of the report approved by the Commission relating to the independent safety assessment of the facility of the licensee submitted under paragraph (5)(D).

(7)

Authorization of appropriations

There is authorized to be appropriated to carry out this subsection $10,000,000 for each of fiscal years 2008 through 2012, to remain available until expended.

.