The SENSE Act sets up how the EPA Administrator can create and enforce air‑pollution limits for existing power plants that burn coal‑refuse waste to generate electricity. It applies only to units already operating that use fluidized‑bed technology and get at least 75% of their fuel from coal refuse. The law lets plant operators choose to meet either a hydrogen chloride (HCl) limit or a sulfur dioxide (SO₂) limit, but not both, and defines the specific emission caps they must stay under.

Key Provisions

  • Defines key terms such as “coal‑refuse electric utility steam generating unit,” which must be in operation, use fluidized‑bed combustion, and burn at least 75% coal‑refuse.
  • Allows the EPA Administrator to require operators to comply with either an HCl standard or an SO₂ standard, but not both, for units covered under the Clean Air Act.
  • Sets the HCl limits at either 0.002 pounds per million Btu of heat input or 0.02 pounds per megawatt‑hour, whichever the operator selects.
  • Sets the SO₂ limits at either 0.20 pounds per million Btu, 1.5 pounds per megawatt‑hour, or a performance‑based rule requiring 93% capture of SO₂ based on fuel testing and continuous emissions monitoring.
  • Requires that compliance be measured using a 30‑day rolling average of boiler operating days for each unit or group of units at a single facility.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

23 earlier actions
SenateIntro Referral Latest Action

Received in the Senate and Read twice and referred to the Committee on Environment and Public Works.

March 8, 2018

View full timeline
HouseIntro Referral

Introduced in House

February 16, 2017

HouseIntro Referral

Sponsor introductory remarks on measure. (CR H1282-1283)

February 16, 2017

HouseIntro Referral

Referred to the House Committee on Energy and Commerce.

February 16, 2017

HouseCommittee

Referred to the Subcommittee on Environment.

February 17, 2017

HouseCommittee

Subcommittee Consideration and Mark-up Session Held.

November 15, 2017

HouseCommittee

Forwarded by Subcommittee to Full Committee (Amended) by the Yeas and Nays: 13 - 10 .

November 15, 2017

HouseCommittee

Committee Consideration and Mark-up Session Held.

December 6, 2017

HouseCommittee

Ordered to be Reported (Amended) by the Yeas and Nays: 31 - 23.

December 6, 2017

HouseCommittee

Reported (Amended) by the Committee on Energy and Commerce. H. Rept. 115-514.

January 12, 2018

HouseCalendars

Placed on the Union Calendar, Calendar No. 384.

January 12, 2018

HouseFloor

Rules Committee Resolution H. Res. 762 Reported to House. Rule provides for consideration of H.R. 1119 and H.R. 1917. Rule provides for consideration of H.R. 1119 and H.R. 1917 under closed rules. Each measure shall be debatable for one hour equally divided and controlled by the Chair and Ranking Member of the Committee on Energy and Commerce. The rule provides for one motion to recommit with or without instructions on each measure.

March 5, 2018 • 6:39 PM

HouseFloor

Considered under the provisions of rule H. Res. 762. (consideration: CR H1480-1489)

March 8, 2018 • 9:12 AM

HouseFloor

Rule provides for consideration of H.R. 1119 and H.R. 1917. Rule provides for consideration of H.R. 1119 and H.R. 1917 under closed rules. Each measure shall be debatable for one hour equally divided and controlled by the Chair and Ranking Member of the Committee on Energy and Commerce. The rule provides for one motion to recommit with or without instructions on each measure.

March 8, 2018 • 9:12 AM

HouseFloor

DEBATE - The House proceeded with one hour of debate on H.R. 1119.

March 8, 2018 • 9:14 AM

HouseFloor

The previous question was ordered pursuant to the rule.

March 8, 2018 • 10:00 AM

HouseFloor

Mr. Kildee moved to recommit with instructions to the Committee on Energy and Commerce. (text: CR H1487)

March 8, 2018 • 10:01 AM

HouseFloor

DEBATE - The House proceeded with 10 minutes of debate on the Kildee motion to recommit with instructions. The instructions contained in the motion seek to require the bill to be reported back to the House with an amendment to prevent the underlying bill from applying to any coal refuse electric utility steam generating facility associated with air pollution.

March 8, 2018 • 10:01 AM

HouseFloor

The previous question on the motion to recommit with instructions was ordered without objection.

March 8, 2018 • 10:11 AM

HouseFloor

On motion to recommit with instructions Failed by the Yeas and Nays: 181 - 225 (Roll no. 100).

March 8, 2018 • 10:36 AM

HouseFloor

Passed/agreed to in House: On passage Passed by recorded vote: 215 - 189 (Roll no. 101).(text: CR H1481)

March 8, 2018 • 10:45 AM

HouseFloor

On passage Passed by recorded vote: 215 - 189 (Roll no. 101). (text: CR H1481)

March 8, 2018 • 10:45 AM

HouseFloor

Motion to reconsider laid on the table Agreed to without objection.

March 8, 2018 • 10:45 AM

HouseFloor

The title of the measure was amended. Agreed to without objection.

March 8, 2018 • 10:45 AM

SenateIntro Referral

Received in the Senate and Read twice and referred to the Committee on Environment and Public Works.

March 8, 2018

Amendments

1 amendment

Offered to this bill

Floor Debate

15 members

What members said about H.R. 1119 on the floor

6 Republicans9 Democrats
Keith J. Rothfus
Rep. Keith J. RothfusR-PA-12 · Mar 8, 2018

Mr. Speaker, I thank Chairman Shimkus for leading and his help with this important legislation. This is going to be an interesting debate. This is a debate about one size fits all coming out of…

Liz Cheney
Rep. Liz CheneyR-WY · Mar 7, 2018

Mr. Speaker, by direction of the Committee on Rules, I call up House Resolution 762 and ask for its immediate consideration. Mr. Speaker, for the purpose of debate only, I yield the customary 30…

Alcee L. Hastings
Rep. Alcee L. HastingsD-FL-20 · Mar 7, 2018

Mr. Speaker, I yield myself such time as I may consume. Mr. Speaker, I would like first to thank the gentlewoman from Wyoming (Ms. Cheney), my friend, for yielding me the customary 30 minutes for…

John Shimkus
Rep. John ShimkusR-IL-15 · Mar 8, 2018

Mr. Speaker, pursuant to House Resolution 762, I call up the bill (H.R. 1119) to establish the bases by which the Administrator of the Environmental Protection Agency shall issue, implement, and…

Michael F. Doyle
Rep. Michael F. DoyleD-PA-14 · Mar 8, 2018

Madam Speaker, I rise in opposition to the SENSE Act. This bill is an unnecessary and permanent carve-out for waste coal plants that forfeits scientific and industrial progress. Waste coal plants may…

Show 8 more
Paul Tonko
Rep. Paul TonkoD-NY-20 · Mar 8, 2018

Mr. Speaker, I yield myself such time as I may consume. Mr. Speaker, I rise today in opposition to H.R. 1119, the Satisfying Energy Needs and Saving the Environment, or SENSE, Act. The SENSE Act…

Keith J. Rothfus
Rep. Keith J. RothfusR-PA-12 · Mar 7, 2018

Mr. Speaker, I thank the gentlewoman for yielding time to me. Mr. Speaker, just listening to the other side's comments about the SENSE Act, I am wondering if they have read the same bill or if they…

Daniel T. Kildee
Rep. Daniel T. KildeeD-MI-5 · Mar 8, 2018

Mr. Speaker, I have a motion to recommit at the desk. Mr. Speaker, I am opposed. Mr. Speaker, this is the final amendment to the bill, which will not kill the bill or send it back to committee. If…

Bill Johnson
Rep. Bill JohnsonR-OH-6 · Mar 7, 2018

Mr. Speaker, I appreciate the opportunity to speak. Mr. Speaker, I am actually a little bit confused. I thought this was supposed to be a debate on a rule dealing with overturning onerous EPA…

Frank Pallone, Jr.
Rep. Frank Pallone, Jr.D-NJ-6 · Mar 8, 2018

Mr. Speaker, I rise in opposition to H.R. 1119, the ``Satisfying Energy Needs and Saving the Environment Act''. The SENSE Act continues yesterday's latest effort by Republicans to undermine the…

Jim Costa
Rep. Jim CostaD-CA-16 · Mar 7, 2018

Mr. Speaker, I thank my friend, the gentleman from Florida (Mr. Hastings), for yielding me this time. Mr. Speaker, the United States, as we know, is a nation of immigrants, past and present. For…

Greg Walden
Rep. Greg WaldenR-OR-2 · Mar 8, 2018

Mr. Speaker, ask anyone who lives in or near communities with waste coal piles from abandoned mines and they will tell you that they can be a significant environmental hazard. They can leak acidic…

Keith J. Rothfus
Rep. Keith J. RothfusR-PA-12 · Feb 16, 2017

Mr. Speaker, I rise today to highlight the progress hardworking western Pennsylvanians have made in restoring our hillsides and streams in historic mining communities polluted by waste coal. Through…

Show 4 more
Rosa L. DeLauro
Rep. Rosa L. DeLauroD-CT-3 · Mar 8, 2018

Mr. Speaker, I was unavoidably detained and so I missed rollcall vote No. 100 regarding the Motion to Recommit on H.R. 1119. Had I been present, I would have voted ``yes.'' Mr. Speaker, I was…

Timothy J. Walz
Rep. Timothy J. WalzD-MN-1 · Mar 13, 2018

Mr. Speaker, I was absent for the vote on the Passage of H.R. 4607 (Roll Call No. 95). Had I been present, I would have voted no. I was also absent for the vote on the Passage of H.R. 1119 (Roll Call…

Richard Hudson
Rep. Richard HudsonR-NC-8 · Mar 8, 2018

Mr. Speaker, I was at a medical appointment with my son and was unable to vote, had I been present, I would have voted ``nay'' on rollcall No. 100 and ``yea'' on rollcall No. 101.

André Carson
Rep. André CarsonD-IN-7 · Mar 8, 2018

Mr. Speaker, during rollcall vote No. 101 on H.R. 1119, I mistakenly recorded my vote as ``yea'' when I should have voted ``nay.''

Bill Text

4 versions available

Reading Mode
Latest
Engrossed in HouseIssued March 8, 2018

115th CONGRESS

2d Session

H. R. 1119

AN ACT

To establish the bases by which the Administrator of the Environmental Protection Agency shall issue, implement, and enforce certain emission limitations for existing electric utility steam generating units that convert coal refuse into energy.

1.

Short title

This Act may be cited as the Satisfying Energy Needs and Saving the Environment Act or the SENSE Act.

2.

Standards for coal refuse power plants

(a)

Definitions

In this Act:

(1)

Administrator

The term Administrator means the Administrator of the Environmental Protection Agency.

(2)

Boiler operating day

The term boiler operating day has the meaning given such term in section 63.10042 of title 40, Code of Federal Regulations, or any successor regulation.

(3)

Coal refuse

The term coal refuse means any byproduct of coal mining, physical coal cleaning, or coal preparation operation that contains coal, matrix material, clay, and other organic and inorganic material.

(4)

Coal refuse electric utility steam generating unit

The term coal refuse electric utility steam generating unit means an electric utility steam generating unit that—

(A)

is in operation as of the date of enactment of this Act;

(B)

uses fluidized bed combustion technology to convert coal refuse into energy; and

(C)

uses coal refuse as at least 75 percent of the annual fuel consumed, by heat input, of the unit.

(5)

Coal refuse-fired facility

The term coal refuse-fired facility means all coal refuse electric utility steam generating units that are—

(A)

located on one or more contiguous or adjacent properties;

(B)

specified within the same Major Group (2-digit code), as described in the Standard Industrial Classification Manual (1987); and

(C)

under common control of the same person (or persons under common control).

(6)

Electric utility steam generating unit

The term electric utility steam generating unit means an electric utility steam generating unit, as such term is defined in section 63.10042 of title 40, Code of Federal Regulations, or any successor regulation.

(b)

Emission limitations To address hydrogen chloride and sulfur dioxide as hazardous air pollutants

(1)

Applicability

For purposes of regulating emissions of hydrogen chloride or sulfur dioxide from a coal refuse electric utility steam generating unit under section 112 of the Clean Air Act (42 U.S.C. 7412), the Administrator—

(A)

shall authorize the operator of such unit to elect that such unit comply with either—

(i)

an emissions standard for emissions of hydrogen chloride that meets the requirements of paragraph (2); or

(ii)

an emission standard for emissions of sulfur dioxide that meets the requirements of paragraph (2); and

(B)

may not require that such unit comply with both an emission standard for emissions of hydrogen chloride and an emission standard for emissions of sulfur dioxide.

(2)

Rules for emission limitations

(A)

In general

The Administrator shall require an operator of a coal refuse electric utility steam generating unit to comply, at the election of the operator, with no more than one of the following emission standards:

(i)

An emission standard for emissions of hydrogen chloride from such unit that is no more stringent than an emission rate of 0.002 pounds per million British thermal units of heat input.

(ii)

An emission standard for emissions of hydrogen chloride from such unit that is no more stringent than an emission rate of 0.02 pounds per megawatt-hour.

(iii)

An emission standard for emissions of sulfur dioxide from such unit that is no more stringent than an emission rate of 0.20 pounds per million British thermal units of heat input.

(iv)

An emission standard for emissions of sulfur dioxide from such unit that is no more stringent than an emission rate of 1.5 pounds per megawatt-hour.

(v)

An emission standard for emissions of sulfur dioxide from such unit that is no more stringent than capture and control of 93 percent of sulfur dioxide across the generating unit or group of generating units, as determined by comparing—

(I)

the expected sulfur dioxide generated from combustion of fuels emissions calculated based upon as-fired fuel samples, to

(II)

the actual sulfur dioxide emissions as measured by a sulfur dioxide continuous emission monitoring system.

(B)

Measurement

An emission standard described in subparagraph (A) shall be measured as a 30 boiler operating day rolling average per coal refuse electric utility steam generating unit or group of coal refuse electric utility steam generating units located at a single coal refuse-fired facility.

Passed the House of Representatives March 8, 2018.