H.R. 2274House115th Congress (2017-2019)Passed House

HYPE Act

Introduced May 1, 2017

AI-Generated Summary

Updated April 15, 2026 at 3:10 PM UTC

The HYdropower Permit Extension (HYPE) Act changes the Federal Power Act to give developers of hydroelectric projects more time to hold a preliminary permit and to start building. It lengthens the initial permit period and adds the ability to extend it further, and it also extends the construction deadline for projects that have a permit.

Key Provisions

  • Increases the standard length of a preliminary permit from three years to four years.
  • Allows the Federal Energy Regulatory Commission (FERC) to extend a preliminary permit once for up to four additional years beyond the initial four‑year period.
  • Provides a second possible extension of up to four more years if FERC finds extraordinary circumstances justify it.
  • Extends the time limit for beginning construction on a project from the previous maximum of two additional years to a maximum of eight additional years.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

14 earlier actions
SenateCalendars Latest Action

Received in the Senate. Read twice. Placed on Senate Legislative Calendar under General Orders. Calendar No. 135.

June 13, 2017

View full timeline
HouseIntro Referral

Introduced in House

May 1, 2017

HouseIntro Referral

Referred to the House Committee on Energy and Commerce.

May 1, 2017

HouseCommittee

Referred to the Subcommittee on Energy.

May 5, 2017

HouseCommittee

Committee Consideration and Mark-up Session Held.

June 7, 2017

HouseCommittee

Ordered to be Reported by Unanimous Consent.

June 7, 2017

HouseCommittee

Subcommittee on Energy Discharged.

June 7, 2017

HouseCommittee

Reported by the Committee on Energy and Commerce. H. Rept. 115-173.

June 12, 2017

HouseCalendars

Placed on the Union Calendar, Calendar No. 117.

June 12, 2017

HouseFloor

Mr. Upton moved to suspend the rules and pass the bill.

June 12, 2017 • 4:12 PM

HouseFloor

Considered under suspension of the rules. (consideration: CR H4828-4829)

June 12, 2017 • 4:12 PM

HouseFloor

DEBATE - The House proceeded with forty minutes of debate on H.R. 2274.

June 12, 2017 • 4:12 PM

HouseFloor

Passed/agreed to in House: On motion to suspend the rules and pass the bill Agreed to by voice vote.(text: CR H4829)

June 12, 2017 • 4:16 PM

HouseFloor

On motion to suspend the rules and pass the bill Agreed to by voice vote. (text: CR H4829)

June 12, 2017 • 4:16 PM

HouseFloor

Motion to reconsider laid on the table Agreed to without objection.

June 12, 2017 • 4:16 PM

SenateCalendars

Received in the Senate. Read twice. Placed on Senate Legislative Calendar under General Orders. Calendar No. 135.

June 13, 2017

Floor Debate

3 members

What members said about H.R. 2274 on the floor

1 Republican2 Democrats
Scott H. Peters
Rep. Scott H. PetersD-CA-52 · Jun 12, 2017

Mr. Speaker, hydropower is one of the few carbon-free energy sources that provides a steady baseload of electricity. Producing more electricity from hydropower helps us meet our clean energy goals…

Diana DeGette
Rep. Diana DeGetteD-CO-1 · Jun 12, 2017

Mr. Speaker, I yield myself such time as I may consume. Mr. Speaker, I rise in support of H.R. 2274, the HYdropower Permit Extension, or HYPE, Act. I am pleased that the House is considering this…

Fred Upton
Rep. Fred UptonR-MI-6 · Jun 12, 2017

Mr. Speaker, I move to suspend the rules and pass the bill (H.R. 2274) to amend the Federal Power Act to provide for extended periods relating to preliminary permits and commencement of construction,…

Bill Text

4 versions available

Reading Mode
Latest
Placed on Calendar SenateIssued June 13, 2017

II

Calendar No. 135

115th CONGRESS

1st Session

H. R. 2274

IN THE SENATE OF THE UNITED STATES

June 13, 2017

Received; read twice and placed on the calendar

AN ACT

To amend the Federal Power Act to provide for extended periods relating to preliminary permits and commencement of construction, and for other purposes.

1.

Short title

This Act may be cited as the HYdropower Permit Extension Act or the HYPE Act.

2.

Extensions of periods

(a)

Preliminary permits

Section 5 of the Federal Power Act (16 U.S.C. 798) is amended—

(1)

in subsection (a), by striking three and inserting four; and

(2)

in subsection (b)—

(A)

by striking Commission may extend the period of a preliminary permit once for not more than 2 additional years beyond the 3 years and inserting the following:

Commission may—

(1)

extend the period of a preliminary permit once for not more than 4 additional years beyond the 4 years

;

(B)

by striking the period at the end and inserting ; and; and

(C)

by adding at the end the following:

(2)

if the period of a preliminary permit is extended under paragraph (1), extend the period of such preliminary permit once for not more than 4 additional years beyond the extension period granted under paragraph (1), if the Commission determines that there are extraordinary circumstances that warrant such additional extension.

.

(b)

Time limit for construction of project works

Section 13 of the Federal Power Act (16 U.S.C. 806) is amended in the second sentence by striking once but not longer than two additional years and inserting for not more than 8 additional years,.

Passed the House of Representatives June 12, 2017.

Karen L. Haas,

Clerk.

June 13, 2017

Received; read twice and placed on the calendar