H.R. 2880House115th Congress (2017-2019)Passed House

Promoting Closed-Loop Pumped Storage Hydropower Act

Introduced June 12, 2017

AI-Generated Summary

Updated April 15, 2026 at 4:35 PM UTC

The Promoting Closed-Loop Pumped Storage Hydropower Act would change the Federal Power Act to speed up licensing for closed‑loop pumped‑storage hydro projects. It creates a fast‑track process, sets safety and environmental checks, and allows certain regulatory exemptions while involving federal, state, and tribal agencies. The bill mainly affects developers of pumped‑storage facilities, the Federal Energy Regulatory Commission, and related wildlife and water agencies.

Key Provisions

  • The Federal Energy Regulatory Commission (FERC) must issue a rule within 180 days establishing an expedited licensing and permit process for closed‑loop pumped‑storage projects, with a final decision required within two years of a complete application.
  • FERC must convene an interagency task force—including federal, state, and tribal representatives—to coordinate the various authorizations needed for these projects.
  • Before licensing, FERC must assess the safety of any existing dams or structures linked to the project.
  • FERC can grant exemptions from other Federal Power Act requirements for parts of a closed‑loop project (excluding dams), but must consult with the U.S. Fish and Wildlife Service and the relevant state wildlife agency and attach protective conditions for fish and wildlife.
  • Applicants must pay fees that reimburse fish‑ and wildlife‑agency costs for required studies; the fees are transferred to those agencies for use on those studies.
  • FERC may add joint permittees after a preliminary permit is issued and can transfer portions of a license to non‑municipal co‑licensees, provided the municipality keeps majority ownership.
  • Communications among agencies during the NEPA environmental review process will not be treated as improper (ex‑parte) communications and will not block agency participation.
  • Within six months, FERC must hold a workshop to explore using abandoned mine sites for closed‑loop pumped storage, and within one year must issue guidance for such projects.
  • FERC must set criteria for projects to qualify for the fast‑track, requiring minimal changes to surface and groundwater flows and little risk to threatened or endangered species.
  • Annual charges owed by licensees will begin when construction of the facility starts, rather than at another earlier point.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

14 earlier actions
SenateIntro Referral Latest Action

Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.

December 13, 2017

View full timeline
HouseIntro Referral

Introduced in House

June 12, 2017

HouseIntro Referral

Referred to the House Committee on Energy and Commerce.

June 12, 2017

HouseCommittee

Referred to the Subcommittee on Energy.

June 16, 2017

HouseCommittee

Forwarded by Subcommittee to Full Committee by Voice Vote .

October 26, 2017

HouseCommittee

Committee Consideration and Mark-up Session Held.

December 6, 2017

HouseCommittee

Ordered to be Reported (Amended) by Voice Vote.

December 6, 2017

HouseCommittee

Reported (Amended) by the Committee on Energy and Commerce. H. Rept. 115-458.

December 11, 2017

HouseCalendars

Placed on the Union Calendar, Calendar No. 340.

December 11, 2017

HouseFloor

Mr. Upton moved to suspend the rules and pass the bill, as amended.

December 12, 2017 • 2:06 PM

HouseFloor

Considered under suspension of the rules. (consideration: CR H9812-9814)

December 12, 2017 • 2:06 PM

HouseFloor

DEBATE - The House proceeded with forty minutes of debate on H.R. 2880.

December 12, 2017 • 2:06 PM

HouseFloor

Passed/agreed to in House: On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote.(text: CR H9812)

December 12, 2017 • 2:20 PM

HouseFloor

On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote. (text: CR H9812)

December 12, 2017 • 2:20 PM

HouseFloor

Motion to reconsider laid on the table Agreed to without objection.

December 12, 2017 • 2:20 PM

SenateIntro Referral

Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.

December 13, 2017

Floor Debate

18 members

What members said about H.R. 2880 on the floor

12 Republicans6 Democrats
Bobby L. Rush
Rep. Bobby L. RushD-IL-1 · Nov 8, 2017

Mr. Chairman, I yield myself such time as I may consume. Mr. Chairman, I rise in strong opposition to H.R. 3043, the Hydropower Policy Modernization Act of 2017. Mr. Chairman, while Members on both…

Fred Upton
Rep. Fred UptonR-MI-6 · Nov 8, 2017

Mr. Speaker, I ask unanimous consent that all Members may have 5 legislative days to revise and extend their remarks and include in the Record extraneous material on H.R. 3043. Mr. Chairman, I yield…

Greg Walden
Rep. Greg WaldenR-OR-2 · Nov 8, 2017

Mr. Chairman, I want to draw attention, first of all, to page 17, line 23, of the bill because we have heard from those who oppose it that somehow this could adversely undermine the Federal Water…

Frank Pallone, Jr.
Rep. Frank Pallone, Jr.D-NJ-6 · Nov 8, 2017

Mr. Chair, I thank Mr. Rush, our ranking member of the subcommittee, for yielding. Mr. Chair, I rise in strong opposition to H.R. 3043. I support hydropower. It can deliver low-carbon, affordable…

H. Morgan Griffith
Rep. H. Morgan GriffithR-VA-9 · Nov 8, 2017

Mr. Chairman, hydropower is an essential component of an all-of-the-above energy strategy. We have a tremendous opportunity to expand renewable hydropower production. However, without some…

Show 8 more
Fred Upton
Rep. Fred UptonR-MI-6 · Dec 12, 2017

Mr. Speaker, I move to suspend the rules and pass the bill (H.R. 2872) to amend the Federal Power Act to promote hydropower development at existing nonpowered dams, and for other purposes, as…

Greg Walden
Rep. Greg WaldenR-OR-2 · Dec 12, 2017

Mr. Speaker, I thank my colleagues on both sides of the aisle for their great work on this: Mr. Rush from Illinois and, of course, the former chairman of the Energy and Commerce Committee, my friend,…

Glenn Grothman
Rep. Glenn GrothmanR-WI-6 · Nov 8, 2017

Mr. Chair, as the designee of my friend and colleague, Mr. Pocan, I have an amendment at the desk. Mr. Chair, first of all, I would like to thank the chair and ranking member for their collaborative…

Paul Tonko
Rep. Paul TonkoD-NY-20 · Nov 8, 2017

Mr. Chairman, I thank the ranking member of our subcommittee, the gentleman from Illinois, for his leadership and hard work on the subcommittee and for yielding me this time. Mr. Chairman, I want to…

Bobby L. Rush
Rep. Bobby L. RushD-IL-1 · Dec 12, 2017

Mr. Speaker, I yield myself such time as I may consume. Mr. Speaker, I rise in strong support of H.R. 2880, the Promoting Closed-Loop Pumped Storage Hydropower Act. Mr. Speaker, as I have stated many…

Tom Cole
Rep. Tom ColeR-OK-4 · Nov 8, 2017

Mr. Chair, I rise today in opposition to H.R. 3043, the Hydropower Policy Modernization Act of 2017. However, I would like to point out the positive outcomes this bill would provide to the Hydropower…

Bobby L. Rush
Rep. Bobby L. RushD-IL-1 · Dec 12, 2017

Mr. Speaker, I yield myself such time as I may consume. Mr. Speaker, I rise in strong support of H.R. 2872, the Promoting Hydropower Development at Existing Nonpowered Dams Act. Mr. Speaker, I…

Fred Upton
Rep. Fred UptonR-MI-6 · Dec 12, 2017

Mr. Speaker, I move to suspend the rules and pass the bill (H.R. 2880) to amend the Federal Power Act to promote closed-loop pumped storage hydropower, and for other purposes, as amended. Mr.…

Show 11 more
Brian Babin
Rep. Brian BabinR-TX-36 · Nov 8, 2017

Mr. Chairman, I have an amendment at the desk. Mr. Chairman, when a disaster like Hurricane Harvey strikes, the most important job we have is to assist those in harm's way. From the Texas National…

Clay Higgins
Rep. Clay HigginsR-LA-3 · Nov 8, 2017

Mr. Chairman, I rise today in support of amendment No. 2 to the Hydropower Policy Modernization Act of 2017, offered by my friend, Representative Babin of Texas. My colleague's amendment, of which I…

Paul A. Gosar
Rep. Paul A. GosarR-AZ-4 · Nov 8, 2017

Mr. Chairman, I rise today in strong support of H.R. 3043 from Representative McMorris Rodgers, the Hydropower Policy Modernization Act of 2017. For centuries, Western States have fought over scarce…

Doug Lamborn
Rep. Doug LambornR-CO-5 · Nov 8, 2017

Mr. Chairman, I rise today in support of H.R. 3043, the Hydropower Policy Modernization Act of 2017, sponsored by the gentlewoman from the State of Washington (Mrs. McMorris Rodgers). This bill…

Jeff Denham
Rep. Jeff DenhamR-CA-10 · Nov 8, 2017

Mr. Chair, I rise in support of H.R. 3043, the Hydropower Modernization Act of 2017. In my area of California's Central Valley, we have the Turlock and Modesto Irrigation Districts. They have been…

Evan H. Jenkins
Rep. Evan H. JenkinsR-WV-3 · Nov 8, 2017

Mr. Chairman, I have an amendment at the desk. Mr. Chairman, my amendment is very straightforward. It supports the mission of the underlying bill to responsibly increase opportunities for hydropower…

Raul Ruiz
Rep. Raul RuizD-CA-36 · Nov 8, 2017

Mr. Chairman, I rise in strong opposition to H.R. 3043, the Hydropower Policy Modernization Act, which undercuts Federal-Tribal treaty and trust obligations. In fact, parts of this bill specifically…

H. Morgan Griffith
Rep. H. Morgan GriffithR-VA-9 · Dec 12, 2017

Mr. Speaker, I want to thank Chairman Walden and Chairman Upton for their cooperation and input. The teams on both sides of the aisle, the chairman of the full committee, and the chairman of the…

Jim Costa
Rep. Jim CostaD-CA-16 · Nov 8, 2017

Mr. Chair, I thank the gentleman from Illinois for yielding. Mr. Chair, I rise in support of H.R. 3043, the Hydropower Policy Modernization Act. Mr. Chair, I believe, and I think others do as well…

Larry Bucshon
Rep. Larry BucshonR-IN-8 · Dec 12, 2017

Mr. Speaker, I thank the gentleman for yielding. Whether it is turning on the light above the kitchen table in a home or powering heavy machinery in a factory, the American people expect there to be…

John P. Sarbanes
Rep. John P. SarbanesD-MD-3 · Nov 8, 2017

Mr. Chairman, I thank the gentleman for yielding. Mr. Chair, I rise in opposition to the Hydropower Policy Modernization Act of 2017 because it weakens States' rights to protect their own water…

Bill Text

4 versions available

Reading Mode
Latest
Referred in SenateIssued December 13, 2017

IIB

115th CONGRESS

1st Session

H. R. 2880

IN THE SENATE OF THE UNITED STATES

December 13, 2017

Received; read twice and referred to the Committee on Energy and Natural Resources

AN ACT

To amend the Federal Power Act to promote closed-loop pumped storage hydropower, and for other purposes.

1.

Short title

This Act may be cited as the Promoting Closed-Loop Pumped Storage Hydropower Act.

2.

Closed-loop pumped storage projects

Part I of the Federal Power Act (16 U.S.C. 792 et seq.) is amended by adding at the end the following:

34.

Closed-loop pumped storage projects

(a)

Expedited licensing process for closed-Loop pumped storage projects

(1)

In general

As provided in this section, the Commission may issue and amend licenses and preliminary permits, as appropriate, for closed-loop pumped storage projects.

(2)

Rule

Not later than 180 days after the date of enactment of this section, the Commission shall issue a rule establishing an expedited process for issuing and amending licenses and preliminary permits for closed-loop pumped storage projects under this section.

(3)

Interagency Task Force

In establishing the expedited process under this section, the Commission shall convene an interagency task force, with appropriate Federal and State agencies and Indian tribes represented, to coordinate the regulatory processes associated with the authorizations required to construct and operate closed-loop pumped storage projects.

(4)

Length of Process

The Commission shall ensure that the expedited process under this section will result in final decision on an application for a license by not later than 2 years after receipt of a completed application for such license.

(b)

Dam safety

Before issuing any license for a closed-loop pumped storage project, the Commission shall assess the safety of existing dams and other structures related to the project (including possible consequences associated with failure of such structures).

(c)

Exemptions from other requirements

(1)

In general

In issuing or amending a license or preliminary permit pursuant to the expedited process established under this section, the Commission may grant an exemption from any other requirement of this part with respect to any part of the closed-loop pumped storage project (not including any dam or other impoundment).

(2)

Consultation

In granting an exemption under paragraph (1), the Commission shall consult with the United States Fish and Wildlife Service and the State agency exercising administration over the fish and wildlife resources of the State in which the closed-loop pumped storage project is or will be located, in the manner provided by the Fish and Wildlife Coordination Act (16 U.S.C. 661 et seq.).

(3)

Terms and conditions

In granting an exemption under paragraph (1), the Commission shall include in any such exemption—

(A)

such terms and conditions as the Fish and Wildlife Service, National Marine Fisheries Service, and the State agency described in paragraph (2) each determine are appropriate to prevent loss of, or damage to, fish and wildlife resources and to otherwise carry out the purposes of the Fish and Wildlife Coordination Act; and

(B)

such terms and conditions as the Commission deems appropriate to ensure that such closed-loop pumped storage project continues to comply with the provisions of this section and terms and conditions included in any such exemption.

(4)

Fees

The Commission, in addition to the requirements of section 10(e), shall establish fees which shall be paid by an applicant for a license for a closed-loop pumped storage project that is required to meet terms and conditions set by fish and wildlife agencies under paragraph (3). Such fees shall be adequate to reimburse the fish and wildlife agencies referred to in paragraph (3) for any reasonable costs incurred in connection with any studies or other reviews carried out by such agencies for purposes of compliance with this section. The fees shall, subject to annual appropriations Acts, be transferred to such agencies by the Commission for use solely for purposes of carrying out such studies and shall remain available until expended.

(d)

Transfers

Notwithstanding section 5, and regardless of whether the holder of a preliminary permit for a closed-loop pumped storage project claimed municipal preference under section 7(a) when obtaining the permit, the Commission may, to facilitate development of a closed-loop pumped storage project—

(1)

add entities as joint permittees following issuance of a preliminary permit; and

(2)

transfer a license in part to one or more nonmunicipal entities as co-licensees with a municipality, if the municipality retains majority ownership of the project for which the license was issued.

(e)

Interagency communications

Interagency cooperation in the preparation of environmental documents under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) with respect to an application for a license for a closed-loop pumped storage project submitted pursuant to this section, and interagency communications relating to licensing process coordination pursuant to this section, shall not—

(1)

be considered to be ex parte communications under Commission rules; or

(2)

preclude an agency from participating in a licensing proceeding under this part.

(f)

Developing abandoned mines for pumped storage

(1)

Workshop

Not later than 6 months after the date of enactment of this section, the Commission shall hold a workshop to explore potential opportunities for development of closed-loop pumped storage projects at abandoned mine sites.

(2)

Guidance

Not later than 1 year after the date of enactment of this section, the Commission shall issue guidance to assist applicants for licenses or preliminary permits for closed-loop pumped storage projects at abandoned mine sites.

(g)

Qualifying criteria for closed-Loop pumped storage projects

(1)

In general

The Commission shall establish criteria that a pumped storage project shall meet in order to qualify as a closed-loop pumped storage project eligible for the expedited process established under this section.

(2)

Inclusions

In establishing the criteria under paragraph (1), the Commission shall include criteria requiring that the pumped storage project—

(A)

cause little to no change to existing surface and groundwater flows and uses; and

(B)

is unlikely to adversely affect species listed as a threatened species or endangered species under the Endangered Species Act of 1973.

.

3.

Obligation for payment of annual charges

Section 10(e) of the Federal Power Act (16 U.S.C. 803(e)) is amended by adding at the end the following:

(5)

Any obligation of a licensee for payment of annual charges under this subsection shall commence when the construction of the applicable facility commences.

.

Passed the House of Representatives December 12, 2017.

Karen L. Haas,

Clerk