The Billion Dollar Boondoggle Act of 2023 directs the Office of Management and Budget (OMB) to require federal agencies to report annually on any major projects that are significantly over budget or far behind schedule. It aims to increase transparency and oversight of costly, delayed government projects. The reporting requirement applies to executive and independent regulatory agencies and informs Congress about project performance.

Key Provisions

  • Defines a "covered agency" as any executive or independent regulatory agency and a "covered project" as one that is more than five years behind schedule or exceeds its original cost estimate by at least $1 billion.
  • Mandates that OMB issue guidance within one year of the law’s enactment requiring covered agencies to submit annual reports on each covered project.
  • Specifies the information agencies must include for each project, such as purpose, location, contract details, start year, federal cost share, and primary contractors.
  • Requires agencies to provide original and current expected completion dates, original and current cost estimates (adjusted for inflation), and explanations for delays or cost overruns.
  • Calls for disclosure of any awards, incentive fees, or bonuses associated with the project.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

1 earlier action
HouseIntro Referral Latest Action

Referred to the Committee on Oversight and Accountability, and in addition to the Committee on Armed Services, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.

February 24, 2023

View full timeline
HouseIntro Referral

Introduced in House

February 24, 2023

HouseIntro Referral

Referred to the Committee on Oversight and Accountability, and in addition to the Committee on Armed Services, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.

February 24, 2023

Bill Text

Latest available legislative text

Reading Mode
Latest
Introduced in HouseIssued February 24, 2023

I

118th CONGRESS

1st Session

H. R. 1180

IN THE HOUSE OF REPRESENTATIVES

February 24, 2023

Mr. Gallagher (for himself and Ms. Porter) introduced the following bill; which was referred to the Committee on Oversight and Accountability, and in addition to the Committee on Armed Services, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned

A BILL

To require the Director of the Office of Management and Budget to submit to Congress an annual report on projects that are over budget and behind schedule, and for other purposes.

1.

Short title

This Act may be cited as the Billion Dollar Boondoggle Act of 2023.

2.

Annual report

(a)

Definitions

In this section—

(1)

the term covered agency means—

(A)

an Executive agency, as defined in section 105 of title 5, United States Code; and

(B)

an independent regulatory agency, as defined in section 3502 of title 44, United States Code;

(2)

the term covered project means a project funded by a covered agency—

(A)

that is more than 5 years behind schedule; or

(B)

for which the amount spent on the project is not less than $1,000,000,000 more than the original cost estimate for the project; and

(3)

the term project means a major acquisition, a major defense acquisition program (as defined in section 2430 of title 10, United States Code), a procurement, a construction project, a remediation or clean-up effort, or any other time-limited endeavor, that is not funded through direct spending (as defined in section 250(c) of the Balanced Budget and Emergency Deficit Control Act of 1985 (2 U.S.C. 900(c)).

(b)

Requirement

Not later than 1 year after the date of enactment of this Act, the Director of the Office of Management and Budget shall issue guidance requiring covered agencies to include, on an annual basis in a report described in paragraph (2) of section 3516(a) of title 31, United States Code, or a consolidated report described in paragraph (1) of such section, information relating to each covered project of the covered agency, which shall include—

(1)

a brief description of the covered project, including—

(A)

the purpose of the covered project;

(B)

each location in which the covered project is carried out;

(C)

the contract or award number of the covered project, where applicable;

(D)

the year in which the covered project was initiated;

(E)

the Federal share of the total cost of the covered project; and

(F)

each primary contractor, subcontractor, grant recipient, and subgrantee recipient of the covered project;

(2)

an explanation of any change to the original scope of the covered project, including by the addition or narrowing of the initial requirements of the covered project;

(3)

the original expected date for completion of the covered project;

(4)

the current expected date for completion of the covered project;

(5)

the original cost estimate for the covered project, as adjusted to reflect increases in the Consumer Price Index for All Urban Consumers, as published by the Bureau of Labor Statistics;

(6)

the current cost estimate for the covered project, as adjusted to reflect increases in the Consumer Price Index for All Urban Consumers, as published by the Bureau of Labor Statistics;

(7)

an explanation for a delay in completion or an increase in the original cost estimate for the covered project, including, where applicable, any impact of insufficient or delayed appropriations; and

(8)

the amount of and rationale for any award, incentive fee, or other type of bonus, if any, awarded for the covered project.