H.R. 3415House118th Congress (2023-2025)Passed House

Pilot Butte Power Plant Conveyance Act

Introduced May 17, 2023

AI-Generated Summary

Updated January 20, 2026 at 7:50 AM UTC

The Pilot Butte Power Plant Conveyance Act directs the Interior Secretary to transfer ownership of the Pilot Butte Power Plant in Wyoming to the Midvale Irrigation District. The district will take over operation, maintenance, and liability, while the federal government retains no ownership. The bill sets out how the transfer, costs, and legal responsibilities will be handled.

Key Provisions

  • The Secretary must negotiate an agreement with the district within two years to define the legal and financial terms of the transfer.
  • The power plant, including land and facilities, will be conveyed to the district, subject to existing leases, permits, and rights‑of‑way.
  • Upon conveyance, the district assumes all liability for the plant and the site is no longer part of a federal reclamation project.
  • The United States limits its liability for damages after the transfer, except for negligence as allowed by law.
  • Both the Secretary and the district share equally the administrative, real‑estate, and environmental compliance costs associated with the conveyance.
  • The district must comply with all applicable federal, state, and local laws when operating the plant, and the Secretary must satisfy NEPA, Endangered Species Act, historic preservation, and other required reviews before the transfer.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

18 earlier actions
SenateIntro Referral Latest Action

Received in the Senate.

February 8, 2024

View full timeline
HouseIntro Referral

Introduced in House

May 17, 2023

HouseIntro Referral

Referred to the House Committee on Natural Resources.

May 17, 2023

HouseCommittee

Referred to the Subcommittee on Water, Wildlife, and Fisheries.

June 9, 2023

HouseCommittee

Subcommittee Hearings Held.

September 28, 2023

HouseCommittee

Committee Consideration and Mark-up Session Held.

October 25, 2023

HouseCommittee

Subcommittee on Water, Wildlife, and Fisheries Discharged.

October 26, 2023

HouseCommittee

Committee Consideration and Mark-up Session Held.

October 26, 2023

HouseCommittee

Ordered to be Reported by Unanimous Consent.

October 26, 2023

HouseCommittee

Reported by the Committee on Natural Resources. H. Rept. 118-367.

January 30, 2024

HouseCalendars

Placed on the Union Calendar, Calendar No. 300.

January 30, 2024

HouseFloor

Mr. Westerman moved to suspend the rules and pass the bill.

February 5, 2024 • 4:26 PM

HouseFloor

Considered under suspension of the rules. (consideration: CR H398-400)

February 5, 2024 • 4:26 PM

HouseFloor

DEBATE - The House proceeded with forty minutes of debate on H.R. 3415.

February 5, 2024 • 4:26 PM

HouseFloor

At the conclusion of debate, the chair put the question on the motion to suspend the rules. Mr. Westerman objected to the vote on the grounds that a quorum was not present. Further proceedings on the motion were postponed. The point of no quorum was considered as withdrawn.

February 5, 2024 • 4:35 PM

HouseFloor

Considered as unfinished business. (consideration: CR H519)

February 7, 2024 • 11:17 AM

HouseFloor

Passed/agreed to in House: On motion to suspend the rules and pass the bill Agreed to by voice vote. (text: 02/05/2024 CR H399)

February 7, 2024 • 11:18 AM

HouseFloor

On motion to suspend the rules and pass the bill Agreed to by voice vote. (text: 02/05/2024 CR H399)

February 7, 2024 • 11:18 AM

HouseFloor

Motion to reconsider laid on the table Agreed to without objection.

February 7, 2024 • 11:18 AM

SenateIntro Referral

Received in the Senate.

February 8, 2024

Floor Debate

6 members

What members said about H.R. 3415 on the floor

3 Republicans3 Democrats
John Barrasso
Sen. John BarrassoR-WY · Dec 18, 2024

Madam President, I rise today to pass important legislation in the State of Wyoming. This bill has only to do with Wyoming and no other State. It is H.R. 3415, the Pilot Butte Power Plant Conveyance…

Harriet M. Hageman
Rep. Harriet M. HagemanR-WY · Feb 5, 2024

Mr. Speaker, I rise in support of my bill, the Pilot Butte Power Plant Conveyance Act. This important legislation initiates the transfer of the Pilot Butte Power Plant from the Bureau of Reclamation…

Bruce Westerman
Rep. Bruce WestermanR-AR-4 · Feb 5, 2024

Mr. Speaker, I move to suspend the rules and pass the bill (H.R. 3415) to direct the Secretary of the Interior to convey to the Midvale Irrigation District the Pilot Butte Power Plant in the State of…

Catherine Cortez Masto
Sen. Catherine Cortez MastoD-NV · Dec 18, 2024

Madam President, I rise today to thank Senator Barrasso and my colleagues on Energy and Natural Resources. Today, we were able to pass H.R. 5443, which is the Accelerating Appraisals and Conservation…

Tina Smith
Sen. Tina SmithD-MN · Dec 18, 2024

Madam President, reserving the right to object, I want to say that I understand that Senator Heinrich from New Mexico has concerns about the Pilot Butte Power Plant Conveyance Act, and I share his…

Show 1 more
Debbie Dingell
Rep. Debbie DingellD-MI-6 · Feb 5, 2024

Mr. Speaker, I yield myself such time as I may consume. Mr. Speaker, this bill would authorize the Bureau of Reclamation to convey the title of the Pilot Butte Power Plant in Wyoming to the Midvale…

Bill Text

4 versions available

Reading Mode
Latest
Received in SenateIssued February 8, 2024

II

118th CONGRESS

2d Session

H. R. 3415

IN THE SENATE OF THE UNITED STATES

February 8 (legislative day, February 7), 2024

Received

AN ACT

To direct the Secretary of the Interior to convey to the Midvale Irrigation District the Pilot Butte Power Plant in the State of Wyoming, and for other purposes.


1.

Short title

This Act may be cited as the Pilot Butte Power Plant Conveyance Act.

2.

Definitions

In this Act:

(1)

Agreement

The term Agreement means the agreement entered into under section 3(a).

(2)

District

The term District means the Midvale Irrigation District located in Pavillion, Wyoming.

(3)

Power plant

The term Power Plant means the Pilot Butte Power Plant and other appurtenant facilities in the State of Wyoming authorized under the Act of March 2, 1917 (39 Stat. 969, chapter 146), transferred to the jurisdiction of the Bureau of Reclamation under the Act of June 5, 1920 (41 Stat. 874, chapter 235), and incorporated into the Riverton Unit of the Pick-Sloan Missouri Basin Program under Public Law 91–409 (84 Stat. 861), including the underlying land.

(4)

Secretary

The term Secretary means the Secretary of the Interior, acting through the Commissioner of Reclamation.

3.

Agreement, conveyance, and report

(a)

Agreement

Not later than 2 years after the date of enactment of this Act, the Secretary shall enter into good faith negotiations with the District to enter into an agreement to determine the legal, institutional, and financial terms for the conveyance of the Power Plant from the Secretary to the District.

(b)

Conveyance

(1)

In general

In consideration for the District assuming from the United States all liability for the administration, operation, maintenance, and replacement of the Power Plant, the Secretary shall offer to convey and assign to the District all right, title, and interest of the United States in and to the Power Plant—

(A)

subject to valid leases, permits, rights-of-way, easements, and other existing rights; and

(B)

in accordance with—

(i)

the terms and conditions described in the Agreement; and

(ii)

this Act.

(2)

Status of land

Effective on the date of the conveyance of the Power Plant to the District under paragraph (1), the Power Plant shall not be considered to be a part of a Federal reclamation project.

(c)

Report

If the conveyance authorized under subsection (b)(1) is not completed by the date that is 1 year after the date of enactment of this Act, the Secretary shall submit to the Committee on Energy and Natural Resources of the Senate and the Committee on Natural Resources of the House of Representatives a report that describes—

(1)

the status of the conveyance under that subsection;

(2)

any obstacles to completing the conveyance under that subsection; and

(3)

an anticipated date for the completion of the conveyance under that subsection.

4.

Liability

(a)

Damages

Except as otherwise provided by law and for damages caused by acts of negligence committed by the United States or by employees or agents of the United States, effective on the date of the conveyance of the Power Plant to the District under section 3(b)(1), the United States shall not be held liable by any court for damages of any kind arising out of any act, omission, or occurrence relating to the Power Plant.

(b)

Torts Claims

Nothing in this section increases the liability of the United States beyond that provided in chapter 171 of title 28, United States Code (commonly known as the Federal Tort Claims Act).

5.

Compliance with other laws

(a)

Compliance with Environmental and Historic Preservation Laws

Before making the conveyance authorized under section 3(b)(1), the Secretary shall complete all actions required under—

(1)

the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.);

(2)

the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.);

(3)

subtitle III of title 54, United States Code; and

(4)

any other applicable laws.

(b)

Compliance by the District

Effective on the date of the conveyance of the Power Plant to the District under section 3(b)(1), the District shall comply with all applicable Federal, State, and local laws (including regulations) with respect to the operation of the Power Plant.

6.

Payment of costs

(a)

Administrative Costs

Administrative costs for the conveyance of the Power Plant to the District under section 3(b)(1) shall be paid in equal shares by the Secretary and the District.

(b)

Real Estate Transfer Costs

The costs of all boundary surveys, title searches, cadastral surveys, appraisals, and other real estate transactions required for the conveyance of the Power Plant to the District under section 3(b)(1) shall be paid in equal shares by the Secretary and the District.

(c)

Costs of Compliance with Other Laws

The costs associated with any review required under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.), the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.), subtitle III of title 54, United States Code, or any other applicable laws for conveyance of the Power Plant to the District under section 3(b)(1) shall be paid in equal shares by the Secretary and the District.

Passed the House of Representatives February 7, 2024.