S. 465Senate119th Congress (2025-2027)In Committee

GRID Power Act

Introduced February 6, 2025

AI-Generated Summary

Updated November 24, 2025 at 2:57 AM UTC

The GRID Power Act directs the Federal Energy Regulatory Commission to overhaul the interconnection queue so that projects that can reliably dispatch electricity are given priority. By requiring new rules, a fast‑track approval process, and regular reviews, the bill aims to boost grid reliability, resilience, and resource adequacy. It affects transmission providers, independent system operators, regional transmission organizations, and developers of large‑scale dispatchable power projects.

Key Provisions

  • Within 90 days of enactment, FERC must start a rulemaking to fix current interconnection‑request procedures so that new dispatchable power projects can connect faster and cheaper.
  • The rulemaking must let transmission providers (utilities, ISOs, or RTOs) submit proposals to move qualifying dispatchable projects higher in the interconnection queue.
  • Each proposal must show why the project needs priority and how it will improve grid reliability or resilience, include a public‑comment period, and provide regular reports on grid reliability and resilience.
  • FERC must review any proposal and approve or deny it within 60 days of submission.
  • Final regulations implementing these changes must be issued within 180 days of enactment.
  • FERC must review and, if needed, update the regulations at least every five years.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

2 earlier actions
SenateCommittee Latest Action

Committee on Energy and Natural Resources Subcommittee on Energy. Hearings held. With printed Hearing: S.Hrg. 119-366.

April 15, 2026

View full timeline
SenateIntro Referral

Introduced in Senate

February 6, 2025

SenateIntro Referral

Read twice and referred to the Committee on Energy and Natural Resources.

February 6, 2025

SenateCommittee

Committee on Energy and Natural Resources Subcommittee on Energy. Hearings held. With printed Hearing: S.Hrg. 119-366.

April 15, 2026

Bill Text

Latest available legislative text

Reading Mode
Latest
Introduced in SenateIssued February 6, 2025

II

119th CONGRESS

1st Session

S. 465

IN THE SENATE OF THE UNITED STATES

February 6 (legislative day, February 5), 2025

Mr. Hoeven (for himself and Mr. Young) introduced the following bill; which was read twice and referred to the Committee on Energy and Natural Resources

A BILL

To require the Federal Energy Regulatory Commission to reform the interconnection queue process for the prioritization and approval of certain projects, and for other purposes.

1.

Short title

This Act may be cited as the Guaranteeing Reliability through the Interconnection of Dispatchable Power Act or the GRID Power Act.

2.

Definitions

In this Act:

(1)

Bulk-power system

The term bulk-power system has the meaning given the term in section 215(a) of the Federal Power Act (16 U.S.C. 824o(a)).

(2)

Commission

The term Commission means the Federal Energy Regulatory Commission.

(3)

Dispatchable power

The term dispatchable power means an electric energy generation resource capable of providing known and forecastable electric supply in time intervals necessary to ensure grid reliability.

(4)

Grid reliability

The term grid reliability means the ability of the electric grid to deliver an adequate, secure, and stable flow of electricity in the quantity and with the quality demanded by users, taking into account the ability of the bulk-power system to withstand sudden disturbances.

(5)

Grid resilience

The term grid resilience means the ability of the electric grid to adapt to changing physical conditions and withstand and rapidly recover from significant disturbances, including natural disasters, cyber-attacks, and other unforeseen events.

(6)

Independent System Operator

The term Independent System Operator has the meaning given the term in section 3 of the Federal Power Act (16 U.S.C. 796).

(7)

Regional Transmission Organization

The term Regional Transmission Organization has the meaning given the term in section 3 of the Federal Power Act (16 U.S.C. 796).

(8)

Resource adequacy

The term resource adequacy means the ability of the electric system to meet the aggregate electrical demand and energy requirements of end-use customers at all times, accounting for scheduled and reasonably expected unscheduled outages of bulk-power system components.

(9)

Transmission provider

The term transmission provider means—

(A)

a public utility (as defined in section 201(e) of the Federal Power Act (16 U.S.C. 824(e))) that owns, operates, or controls 1 or more transmission facilities;

(B)

an Independent System Operator; and

(C)

a Regional Transmission Organization.

3.

Rulemaking to improve interconnection queue flexibility

(a)

In general

Not later than 90 days after the date of enactment of this Act, the Commission shall initiate a rulemaking—

(1)

to address the inefficiencies and ineffectiveness of existing procedures for processing interconnection requests to ensure that new dispatchable power projects that improve grid reliability and resource adequacy can interconnect to the electric grid quickly, cost-effectively, and reliably; and

(2)

to amend the pro forma Large Generator Interconnection Procedures and, as appropriate, the pro forma Large Generator Interconnection Agreement, promulgated pursuant to section 35.28(f) of title 18, Code of Federal Regulations (or successor regulations)—

(A)

to authorize transmission providers to submit proposals to the Commission to adjust the interconnection queue of the transmission provider to prioritize new dispatchable power projects that will improve grid reliability and resource adequacy by assigning those projects higher positions in the interconnection queue; and

(B)

to require transmission providers—

(i)

to provide in any proposal described in subparagraph (A)—

(I)

a demonstration of need for prioritization of the relevant projects; and

(II)

a description of how the prioritization of those projects will improve grid reliability or grid resilience;

(ii)

to provide a process for public comment and stakeholder engagement before a proposal described in subparagraph (A) is submitted to the Commission; and

(iii)

to provide regular reporting to the Commission on the state of grid reliability and grid resilience, including reporting on any actions taken pursuant to this Act.

(b)

Commission approval

To ensure timely responses to grid reliability concerns, not later than 60 days after a proposal is submitted pursuant to subsection (a)(2), the Commission shall—

(1)

review the proposal; and

(2)

approve or deny the proposal.

(c)

Deadline for final rule

Not later than 180 days after the date of enactment of this Act, the Commission shall promulgate final regulations to complete the rulemaking initiated under subsection (a).

(d)

Periodic review

Not less frequently than once every 5 years, the Commission shall review and, if necessary, update the regulations promulgated under this section to ensure that those regulations remain effective and relevant to evolving grid reliability and grid resilience challenges.