Mr. Chairman, I offer an amendment. Mr. Chairman, this amendment would restore $500,673,000 to the Department of Homeland Security that has been cut entirely from this appropriation. This is the most important construction, private or…
Mr. Chairman, I offer an amendment.
Mr. Chairman, this amendment would restore $500,673,000 to the Department of Homeland Security that has been cut entirely from this appropriation. This is the most important construction, private or public, ongoing in our country today, because it involves a secure facility that the Congress has voted to consolidate in order to protect the United States of America in the homeland.
This entire appropriation cuts billions of dollars in order to reduce spending. I wager that there is no cut quite like this one, because this cut guarantees that the taxpayers will be charged more precisely because of this cut. Already, the reduction in funding to the 2011 appropriation for consolidation of the Department of Homeland Security has cost taxpayers $69 million. Increased costs for this construction of Federal property come from, in this case, lease holdovers, short- term lease extensions, and horrific inefficiencies now imposed because the integration of construction of this mammoth facility will be delayed and interrupted. Any further reduction in funding will substantially increase even more the total costs of this huge project, the largest since the Pentagon. Until now, it was on budget and on time.
Remember why Congress voted to consolidate these 22 agencies in the first place. Congress has never formed one agency of 22 different agencies. They are spread all over this region. That is why the Bush and the Obama administrations and the Congress have pursued a consistent program to consolidate critical elements of the Department of Homeland Security.
These DHS tenants now reside in the most expensive lease space in the United States, because that's what it is in this region, barring none except perhaps New York City. DHS spends hundreds of millions of dollars on leases throughout the entire region. The rapid consolidation of the Department of Homeland Security now underway will save billions, that's B, billions, in real estate costs, in addition to directing lease revenue to the GSA Federal Buildings Fund, which instead of using appropriated taxpayer dollars, uses agency rental payments to fund the construction and maintenance of Federal real estate giving taxpayers added savings.
Currently, DHS is scheduled for full occupation by 2017. Every day of delay costs the taxpayers thousands of dollars. This is no way to do budget cutting. You don't cut what then costs you more in the short term and in the long term.
Significant progress has already been made. Forty-five percent of the construction is complete, including the Coast Guard National Operations Center and the Coast Guard headquarters. You just don't interrupt a massive, complex building like this unless you want to spend more money than was anticipated.
The timing of this amendment is critical to ensure that the project does not increase costs further. The continued dispersal of vital elements of this critically important agency, necessary for our security, undermines the DHS mission by impeding its operations here and throughout the country. We need quickly to fund this project.
Mr. Chair, I rise to offer an amendment to restore funding for the consolidation of the Department of Homeland Security (DHS) headquarters construction at St. Elizabeths in the District of Columbia. This amendment would restore $500,673,000 to the DHS management and operations appropriations account for the project. The amendment would fully fund the President's fiscal year 2012 DHS request for the project, as well as fund the outstanding balance of the President's fiscal year 2011 DHS request.
The reduction in funding in fiscal year 2011 is expected to increase the total project cost by $69 million because of the loss of integrated construction sequencing and efficiencies between the U.S. Coast Guard building and the adjacent DHS Operations Center construction, in addition to the costs caused by lease holdovers and the short-term lease extensions for the delay for Mission Support consolidation. Any further reduction in funding will substantially increase the total cost of this huge project, which, until the cuts began, was on budget and on time.
The benefits of the consolidation of the DHS headquarters at St. Elizabeths are twofold.
First, Congress voted to consolidate the location of 22 DHS agencies because of the urgent need to improve the management of the agencies in the DHS, which are currently scattered in 40 different locations in the Washington metropolitan region. Consequently, the Bush and Obama Administrations and the Congress have pursued a program to consolidate critical elements of DHS on the federally-owned St. Elizabeths Campus. The DHS components identified for consolidation at the headquarters include the Office of the Secretary of the Department of Homeland Security, the Transportation Security Administration, Customs and Border Protection, Immigration and Customs Enforcement, the Federal Emergency Management Agency, the U.S. Coast Guard (USCG) and liaisons for agencies not being relocated there.
Second, the General Services Administration (GSA) will relocate DHS tenants currently in expensive leased space to federally-owned space. DHS annually spends hundreds of millions of dollars for leases throughout the Washington region. The rapid consolidation of DHS, which is now underway, will allow the federal government to save billions of dollars in real estate costs, in addition to directing lease revenue to the GSA Federal Buildings Fund, which, instead of using taxpayer dollars, uses agency rental payments to fund the construction and maintenance of the federal real estate portfolio, an additional saving to taxpayers. The consolidation on St. Elizabeths is expected to include 4.5 million gross square feet of office space, with 3.5 million square feet on the West Campus and 750,000 square feet on the East Campus. Currently, the St. Elizabeths site is scheduled for full occupation in 2017.
The DHS headquarters consolidation is expected to cost a total of $3.6 billion, with $2.2 billion coming from GSA and $1.4 billion from DHS. To date, the project has received $1.24 billion and there has been significant progress, including the groundbreaking for the first building on the site, a 1.2 million square foot project that includes a central utility plant and two seven-story parking garages, that will house the USCG headquarters. There has also been significant investment in the infrastructure of the campus, including construction of a perimeter fence and adaptive reuse of historic buildings. As of March 31, 2011, the USCG headquarters is 45% complete.
Full funding of the FY 2012 request would ensure complete funding for, and allow occupation and use of, the USCG headquarters. My amendment is critical to ensure that the cost of the project does not increase because of delays. The continued dispersal of vital components of DHS, a critically important department, undermines its mission by seriously impeding its operations here and throughout the country. As ranking member of the subcommittee with jurisdiction over GSA and this project, I have held nearly half a dozen hearings and roundtables on the co-location and consolidation of DHS at St. Elizabeths. I am anxious to move forward with this project and look forward to the completion of the consolidation so that DHS can turn its full attention to its core mission.
Unless somebody wants to speak on my amendment, I am prepared to withdraw it.
I appreciate the opportunity to speak, and I withdraw my amendment.