To require a specific authorization of Congress for the commencement of the engineering development phase or subsequent phase of a Robust Nuclear Earth Penetrator.
What it does: Adds SEC. 3135. REQUIREMENT FOR SPECIFIC AUTHORIZATION OF CONGRESS FOR COMMENCEMENT OF ENGINEERING DEVELOPMENT PHASE OR SUBSEQUENT PHASE OF ROBUST NUCLEAR EARTH PENETRATOR at the end of subtitle B of title XXXIWhat it changes
1 change to S. 1050 · shown in the bill's text
Adds SEC. 3135. REQUIREMENT FOR SPECIFIC AUTHORIZATION OF CONGRESS FOR COMMENCEMENT OF ENGINEERING DEVELOPMENT PHASE OR SUBSEQUENT PHASE OF ROBUST NUCLEAR EARTH PENETRATOR at the end of subtitle B of title XXXI
Adds a sectionIn S. 1050 · Placed on Calendar Senate
(c) Repeal of Superseded Plan Requirement.--Subsection (c) of such section is repealed.
Inserted: SEC. 3135. REQUIREMENT FOR SPECIFIC AUTHORIZATION OF CONGRESS FOR COMMENCEMENT OF ENGINEERING DEVELOPMENT PHASE OR SUBSEQUENT PHASE OF ROBUST NUCLEAR EARTH PENETRATOR.
Inserted: The Secretary of Energy may not commence the engineering development phase (phase 6.3) of the nuclear weapons development process, or any subsequent phase, of a Robust Nuclear Earth Penetrator weapon unless specifically authorized by Congress.
Original wording
At the end of subtitle B of title XXXI, add the following:
Read automatically from the Congressional Record. Check the original before relying on it.
As printed
At the end of subtitle B of title XXXI, add the following:
SEC. 3135. REQUIREMENT FOR SPECIFIC AUTHORIZATION OF CONGRESS FOR COMMENCEMENT OF ENGINEERING DEVELOPMENT PHASE OR SUBSEQUENT PHASE OF ROBUST NUCLEAR EARTH PENETRATOR.
The Secretary of Energy may not commence the engineering development phase (phase 6.3) of the nuclear weapons development process, or any subsequent phase, of a Robust Nuclear Earth Penetrator weapon unless specifically authorized by Congress.
Legislative Activity
Stay on top of the latest movement without scrolling through every action
Senate amendment submitted
May 21, 2003
View full timeline
Senate amendment submitted
May 21, 2003
Senate amendment proposed (on the floor): Amendment SA 766 proposed by Senator Nelson FL.(consideration: CR S6805; text: CR S6805)
May 21, 2003
Senate amendment agreed to: Amendment SA 766 agreed to in Senate by Voice.
May 21, 2003
Amendment SA 766 proposed by Senator Nelson FL. (consideration: CR S6805; text: CR S6805) To require a specific authorization of Congress for the commencement of the engineering development phase or subsequent phase of a Robust Nuclear Earth Penetrator.
May 21, 2003
Amendment SA 766 agreed to in Senate by Voice.
May 21, 2003