To avoid a break in production of the Ground-based Interceptor missile until the Department of Defense completes the Ballistic Missile Defense Review and to ensure there is no gap in homeland defense by ensuring that Missile Field 1 at Fort Greely, Alaska, does not complete decommissioning until seven silos have been emplaced at Missile Field 2 at Fort Greely.
What it does: Adds SEC. 245. CONTINUED PRODUCTION OF GROUND-BASED INTERCEPTOR MISSILE AND OPERATION OF MISSILE FIELD 1 AT FORT GREELY, ALASKA at the end of subtitle C of title IIWhat it changes
1 change to S. 1390 · shown in the bill's text
Adds SEC. 245. CONTINUED PRODUCTION OF GROUND-BASED INTERCEPTOR MISSILE AND OPERATION OF MISSILE FIELD 1 AT FORT GREELY, ALASKA at the end of subtitle C of title II
Adds a sectionIn S. 1390 · Placed on Calendar Senate
(6) Such other matters as the Secretary considers appropriate.
Inserted: SEC. 245. CONTINUED PRODUCTION OF GROUND-BASED INTERCEPTOR MISSILE AND OPERATION OF MISSILE FIELD 1 AT FORT GREELY, ALASKA.
Inserted: (a) Limitation on Break in Production.--The Secretary of Defense shall ensure that the Missile Defense Agency does not allow a break in production of the Ground-based Interceptor missile until the Department of Defense has--
Inserted: (1) completed the Ballistic Missile Defense Review; and
Inserted: (2) made a determination with respect to the number of Ground-based Interceptor missiles that will be necessary to support the service life of the Ground-based Midcourse Defense element of the Ballistic Missile Defense System.
Inserted: (b) Limitation on Certain Actions With Respect to Missile Field 1 and Missile Field 2 at Fort Greely, Alaska.--
Inserted: (1) Limitation on decommissioning of missile field 1.--The Secretary of Defense shall ensure that Missile Field 1 at Fort Greely, Alaska, does not complete decommissioning until seven silos have been emplaced at Missile Field 2 at Fort Greely.
Inserted: (2) Limitation with respect to disposition of silos at missile field 2.--The Secretary of Defense shall ensure that no irreversible decision is made with respect to the disposition of operational silos at Missile Field 2 at Fort Greely, Alaska, until that date that is 60 days after the date on which the reports required by subsections (b)(3) and (c)(3) of section 243 are submitted to the congressional defense committees.
Original wording
At the end of subtitle C of title II, add the following:
Read automatically from the Congressional Record. Check the original before relying on it.
As printed
At the end of subtitle C of title II, add the following:
SEC. 245. CONTINUED PRODUCTION OF GROUND-BASED INTERCEPTOR MISSILE AND OPERATION OF MISSILE FIELD 1 AT FORT GREELY, ALASKA.
(a) Limitation on Break in Production.--The Secretary of Defense shall ensure that the Missile Defense Agency does not allow a break in production of the Ground-based Interceptor missile until the Department of Defense has--
(1) completed the Ballistic Missile Defense Review; and
(2) made a determination with respect to the number of Ground-based Interceptor missiles that will be necessary to support the service life of the Ground-based Midcourse Defense element of the Ballistic Missile Defense System.
(b) Limitation on Certain Actions With Respect to Missile Field 1 and Missile Field 2 at Fort Greely, Alaska.--
(1) Limitation on decommissioning of missile field 1.--The Secretary of Defense shall ensure that Missile Field 1 at Fort Greely, Alaska, does not complete decommissioning until seven silos have been emplaced at Missile Field 2 at Fort Greely.
(2) Limitation with respect to disposition of silos at missile field 2.--The Secretary of Defense shall ensure that no irreversible decision is made with respect to the disposition of operational silos at Missile Field 2 at Fort Greely, Alaska, until that date that is 60 days after the date on which the reports required by subsections (b)(3) and (c)(3) of section 243 are submitted to the congressional defense committees.
Legislative Activity
Stay on top of the latest movement without scrolling through every action
Senate amendment proposed (on the floor): Amendment SA 1677 proposed by Senator Levin for Senator Begich.(consideration: CR S7851-7858; text: CR S7858)
July 22, 2009
View full timeline
Senate amendment proposed (on the floor): Amendment SA 1677 proposed by Senator Levin for Senator Begich.(consideration: CR S7851-7858; text: CR S7858)
July 22, 2009
Senate amendment agreed to: Amendment SA 1677 agreed to in Senate by Unanimous Consent.
July 22, 2009
Amendment SA 1677 proposed by Senator Levin for Senator Begich. (consideration: CR S7851-7858; text: CR S7858) To avoid a break in production of the Ground-based Interceptor missile until the Department of Defense completes the Ballistic Missile Defense Review and to ensure there is no gap in homeland defense by ensuring that Missile Field 1 at Fort Greely, Alaska, does not complete decommissioning until seven silos have been emplaced at Missile Field 2 at Fort Greely.
July 22, 2009
Amendment SA 1677 agreed to in Senate by Unanimous Consent.
July 22, 2009
Senate amendment submitted
July 21, 2009