S. 1258Senate118th Congress (2023-2025)Reconciliation

Billion Dollar Boondoggle Act of 2023

Sponsored by Joni ErnstSen. Joni Ernst (R-IA)
Introduced April 25, 2023

AI-Generated Summary

Updated January 20, 2026 at 6:35 AM UTC

The Billion Dollar Boondoggle Act of 2023 directs the Office of Management and Budget to require federal agencies to report annually on any major projects that are more than five years behind schedule or cost at least $1 billion over the original estimate. The goal is to increase transparency about large, over‑budget or delayed government projects. It applies to all executive and independent regulatory agencies that fund such projects.

Key Provisions

  • Defines “covered agencies” as executive and independent regulatory agencies, and “covered projects” as those over $1 billion beyond the original cost estimate or more than five years late.
  • Mandates that OMB issue guidance within one year of enactment requiring agencies to include detailed information on each covered project in an annual report.
  • Requires agencies to report project purpose, locations, contract numbers, start year, federal cost share, contractors, original and current schedules and cost estimates (adjusted for inflation), reasons for delays or cost overruns, and any bonuses or incentives.
  • Allows classified information about a project to be submitted as a classified annex to protect sources and methods.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

14 earlier actions
HouseFloor Latest Action

Motion to reconsider laid on the table Agreed to without objection.

July 22, 2024 • 8:07 PM

View full timeline
SenateIntro Referral

Introduced in Senate

April 25, 2023

SenateIntro Referral

Read twice and referred to the Committee on Homeland Security and Governmental Affairs.

April 25, 2023

SenateCommittee

Committee on Homeland Security and Governmental Affairs. Ordered to be reported without amendment favorably.

October 25, 2023

SenateCommittee

Committee on Homeland Security and Governmental Affairs. Reported by Senator Peters without amendment. With written report No. 118-157.

February 9, 2024

SenateCalendars

Placed on Senate Legislative Calendar under General Orders. Calendar No. 334.

February 9, 2024

SenateFloor

Passed Senate without amendment by Unanimous Consent. (consideration: CR S2616-2617; text: CR S2616-2617)

March 23, 2024

SenateFloor

Message on Senate action sent to the House.

March 25, 2024

HouseFloor

Received in the House.

March 26, 2024 • 9:03 AM

HouseFloor

Held at the desk.

March 26, 2024 • 9:04 AM

HouseFloor

Ms. Mace moved to suspend the rules and pass the bill, as amended.

July 22, 2024 • 8:02 PM

HouseFloor

Considered under suspension of the rules. (consideration: CR H4715-4716)

July 22, 2024 • 8:02 PM

HouseFloor

DEBATE - The House proceeded with forty minutes of debate on S. 1258.

July 22, 2024 • 8:02 PM

SenateFloor

Passed/agreed to in House: On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote. (text: CR H4715)

July 22, 2024 • 8:07 PM

HouseFloor

On motion to suspend the rules and pass the bill, as amended Agreed to by voice vote. (text: CR H4715)

July 22, 2024 • 8:07 PM

HouseFloor

Motion to reconsider laid on the table Agreed to without objection.

July 22, 2024 • 8:07 PM

Floor Debate

4 members

What members said about S. 1258 on the floor

2 Republicans2 Democrats
Nancy Mace
Rep. Nancy MaceR-SC-1 · Jul 22, 2024

Mr. Speaker, I move to suspend the rules and pass the bill (S. 1258) to require the Director of the Office of Management and Budget to submit to Congress an annual report on projects that are over…

Mariannette Miller-Meeks
Rep. Mariannette Miller-MeeksR-IA-1 · Jul 22, 2024

Mr. Speaker, I thank the gentlewoman from South Carolina (Ms. Mace) for yielding me time. Mr. Speaker, I rise today in support of my bill, the Billion Dollar Boondoggle Act, bipartisan legislation…

Jamie Raskin
Rep. Jamie RaskinD-MD-8 · Jul 22, 2024

Mr. Speaker, I yield myself such time as I may consume. Mr. Speaker, the legislation would require additional reporting on certain Federal projects that are over budget by $1 billion or 5 years…

Charles E. Schumer
Sen. Charles E. SchumerD-NY · Mar 22, 2024

Mr. President, I ask unanimous consent that the Senate proceed to the immediate consideration of Calendar No. 334, S. 1258. I further ask that the bill be considered read a third time and passed and…

Bill Text

4 versions available

Reading Mode
Latest
Engrossed Amendment HouseIssued July 22, 2024

118th CONGRESS

2d Session

In the House of Representatives, U. S.,

July 22, 2024

AMENDMENT:

That the bill from the Senate (S. 1258) entitled An Act to require the Director of the Office of Management and Budget to submit to Congress an annual report on projects that are over budget and behind schedule, and for other purposes. , do pass with the following

Strike out all after the enacting clause and insert:

1.

Short title

This Act may be cited as the Billion Dollar Boondoggle Act of 2023.

2.

Annual report

(a)

Definitions

In this section—

(1)

the term covered agency means—

(A)

an Executive agency, as defined in section 105 of title 5, United States Code; and

(B)

an independent regulatory agency, as defined in section 3502 of title 44, United States Code;

(2)

the term covered project means a project funded by a covered agency—

(A)

that is more than 5 years behind schedule, as measured against the original expected date for completion; or

(B)

for which the amount spent on the project is not less than $1,000,000,000 more than the original cost estimate for the project; and

(3)

the term project means a major acquisition, a major defense acquisition program (as defined in section 4201 of title 10, United States Code), a procurement, a construction project, a remediation or clean-up effort, or any other time-limited endeavor, that is not funded through direct spending (as defined in section 250(c) of the Balanced Budget and Emergency Deficit Control Act of 1985 (2 U.S.C. 900(c))).

(b)

Requirement

Not later than 1 year after the date of enactment of this Act, the Director of the Office of Management and Budget shall issue guidance requiring covered agencies to include, on an annual basis in a report described in paragraph (2) of section 3516(a) of title 31, United States Code, or a consolidated report described in paragraph (1) of such section, information relating to each covered project of the covered agency, which shall include—

(1)

a brief description of the covered project, including—

(A)

the purpose of the covered project;

(B)

each location in which the covered project is carried out;

(C)

the contract or award number of the covered project, where applicable;

(D)

the year in which the covered project was initiated;

(E)

the Federal share of the total cost of the covered project; and

(F)

each primary contractor, subcontractor, grant recipient, and subgrantee recipient of the covered project;

(2)

an explanation of any change to the original scope of the covered project, including by the addition or narrowing of the initial requirements of the covered project;

(3)

the original expected date for completion of the covered project;

(4)

the current expected date for completion of the covered project;

(5)

the original cost estimate for the covered project, as adjusted to reflect increases in the Consumer Price Index for All Urban Consumers, as published by the Bureau of Labor Statistics;

(6)

the current cost estimate for the covered project, as adjusted to reflect increases in the Consumer Price Index for All Urban Consumers, as published by the Bureau of Labor Statistics;

(7)

an explanation for a delay in completion or an increase in the original cost estimate for the covered project, including, where applicable, any impact of insufficient or delayed appropriations; and

(8)

the amount of and rationale for any award, incentive fee, or other type of bonus, if any, awarded for the covered project.

(c)

Form

If any information required under subsection (b) is classified, such information may be submitted in the form of a classified annex consistent with the protection of sources and methods.

Clerk.