H.R. 3043House115th Congress (2017-2019)Passed House

Hydropower Policy Modernization Act of 2017

Introduced June 23, 2017

AI-Generated Summary

Updated April 15, 2026 at 4:49 PM UTC

The Hydropower Policy Modernization Act of 2017 updates federal rules to treat hydropower as a renewable energy source and to make it easier and faster to develop, license, and upgrade hydropower projects. It changes definitions, permit timelines, and licensing procedures, and adds new coordination and review requirements for agencies, tribes, and the public.

Key Provisions

  • Adds hydropower to the federal definition of renewable energy and sets a minimum renewable‑energy target of 15% for FY 2017 and later.
  • Extends preliminary permit periods from 3 to 4 years and allows two possible 4‑year extensions; construction time limits are increased to up to 8 additional years.
  • Requires the Federal Energy Regulatory Commission (FERC) to act as lead agency, coordinate all federal, state, local, and tribal authorizations, and set public schedules with deadlines.
  • Creates a trial‑type hearing process (up to 120 days) for disputed “covered measures” such as conditions or fishways.
  • Mandates use of current scientific studies, encourages open‑source tools, and allows watershed‑wide reviews when multiple projects exist.
  • Establishes a fast‑track for “qualifying project upgrades” with specific timelines (public notice, comment, and final action within about 150 days).
  • Requires consideration of invasive‑species threats when prescribing fishways.
  • Allows FERC to review licenses for projects in areas declared disaster zones and to study expansion of non‑federal hydropower under existing inter‑agency agreements.

Legislative Activity

Stay on top of the latest movement without scrolling through every action

30 earlier actions
SenateIntro Referral Latest Action

Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.

November 9, 2017

View full timeline
HouseIntro Referral

Introduced in House

June 23, 2017

HouseIntro Referral

Referred to the Committee on Energy and Commerce, and in addition to the Committee on Oversight and Government Reform, for a period to be subsequently determined by the Speaker, in each case for consideration of such provisions as fall within the jurisdiction of the committee concerned.

June 23, 2017

HouseCommittee

Committee Consideration and Mark-up Session Held.

June 28, 2017

HouseCommittee

Ordered to be Reported (Amended) by Voice Vote.

June 28, 2017

HouseCommittee

Reported (Amended) by the Committee on Energy and Commerce. H. Rept. 115-377, Part I.

October 31, 2017

HouseCommittee

Committee on Oversight and Government discharged.

October 31, 2017

HouseCalendars

Placed on the Union Calendar, Calendar No. 277.

October 31, 2017

HouseFloor

Rules Committee Resolution H. Res. 607 Reported to House. Rule provides for consideration of H.R. 3043 and H.R. 3441. Measure will be considered read. The resolution provides for one hour of debate on H.R. 3043. The resolution makes in order only those further amendments printed in the report and one motion to recommit with or without instructions. Also, the resolution provides for one hour of debate on H.R. 3441 with one motion to recommit with or without instructions.

November 6, 2017 • 7:20 PM

HouseFloor

Considered under the provisions of rule H. Res. 607. (consideration: CR H8614-8641)

November 8, 2017 • 1:43 PM

HouseFloor

Rule provides for consideration of H.R. 3043 and H.R. 3441. Measure will be considered read. The resolution provides for one hour of debate on H.R. 3043. The resolution makes in order only those further amendments printed in the report and one motion to recommit with or without instructions. Also, the resolution provides for one hour of debate on H.R. 3441 with one motion to recommit with or without instructions.

November 8, 2017 • 1:43 PM

HouseFloor

House resolved itself into the Committee of the Whole House on the state of the Union pursuant to H. Res. 607 and Rule XVIII.

November 8, 2017 • 1:43 PM

HouseFloor

The Speaker designated the Honorable Randy Hultgren to act as Chairman of the Committee.

November 8, 2017 • 1:43 PM

HouseFloor

GENERAL DEBATE - The Committee of the Whole proceeded with one hour of general debate on H.R. 3043.

November 8, 2017 • 1:43 PM

HouseFloor

DEBATE - Pursuant to the provisions of H.Res. 607, the Committee of the Whole proceeded with 10 minutes of debate on the Grothman amendment No. 1.

November 8, 2017 • 2:53 PM

HouseFloor

DEBATE - Pursuant to the provisions of H. Res. 607, the Committee of the Whole proceeded with 10 minutes of debate on the Babin amendment No. 2.

November 8, 2017 • 2:58 PM

HouseFloor

DEBATE - Pursuant to the provisions of H. Res. 607, the Committee of the Whole proceeded with 10 minutes of debate on the Jenkins (WV) amendment No. 3.

November 8, 2017 • 3:05 PM

HouseFloor

DEBATE - Pursuant to the provisions of H. Res. 607, the Committee of the Whole proceeded with 10 minutes of debate on the Rush amendment No. 4.

November 8, 2017 • 3:10 PM

HouseFloor

POSTPONED PROCEEDINGS - At the conclusion of debate on the Rush amendment, the Chair put the question on adoption of the amendment and by voice vote announced that the noes had prevailed. Mr. Rush demanded a recorded vote, and the Chair postponed further proceedings on the question of adoption of the amendment until later in the legislative day.

November 8, 2017 • 3:19 PM

HouseFloor

Mr. Upton moved that the Committee rise.

November 8, 2017 • 3:19 PM

HouseFloor

On motion that the Committee rise Agreed to by voice vote.

November 8, 2017 • 3:19 PM

HouseFloor

Committee of the Whole House on the state of the Union rises leaving H.R. 3043 as unfinished business.

November 8, 2017 • 3:19 PM

HouseFloor

Considered as unfinished business. (consideration: CR H8641-8642)

November 8, 2017 • 4:31 PM

HouseFloor

The House resolved into Committee of the Whole House on the state of the Union for further consideration.

November 8, 2017 • 4:31 PM

HouseFloor

UNFINISHED BUSINESS - The Chair announced that the unfinished business was the question on adoption of amendments which had been debated earlier and on which further proceedings had been postponed.

November 8, 2017 • 4:31 PM

HouseFloor

The House rose from the Committee of the Whole House on the state of the Union to report H.R. 3043.

November 8, 2017 • 4:56 PM

HouseFloor

The previous question was ordered pursuant to the rule.

November 8, 2017 • 4:56 PM

HouseFloor

The House adopted the amendment in the nature of a substitute as agreed to by the Committee of the Whole House on the state of the Union.

November 8, 2017 • 4:57 PM

HouseFloor

Passed/agreed to in House: On passage Passed by recorded vote: 257 - 166 (Roll no. 620).(text of amendment in the nature of a substitute: CR H8630-8633)

November 8, 2017 • 5:03 PM

HouseFloor

On passage Passed by recorded vote: 257 - 166 (Roll no. 620). (text of amendment in the nature of a substitute: CR H8630-8633)

November 8, 2017 • 5:03 PM

HouseFloor

Motion to reconsider laid on the table Agreed to without objection.

November 8, 2017 • 5:03 PM

SenateIntro Referral

Received in the Senate and Read twice and referred to the Committee on Energy and Natural Resources.

November 9, 2017

Amendments

4 amendments

Offered to this bill

H.Amdt. 481Nov 8, 2017

Amendment sought to add a new section to the Federal Power Act (FPA) to improve the hydropower licensing process. It sought to direct the Commission and the Federal resource agencies to convene a negotiated rulemaking within 90 days of enactment with named stakeholders to develop a process that would coordinate necessary authorizations and enable the Commission to make a final decision on a license not later than 3 years of receiving a completed license application.

On agreeing to the Rush amendment (A004) Failed by recorded vote: 185 - 234 (Roll no. 619). · Sponsored by Bobby L. Rush

H.Amdt. 480Nov 8, 2017

An amendment numbered 3 printed in House Report 115-391 to ensure that when hydro projects have an existing Memorandum of Understanding for non-federal hydropower with FERC that all relevant federal agencies are authorized to fully study and review the potential expansion of non-federal hydropower, including a review of seasonal pool levels and slowing flood releases.

On agreeing to the Jenkins (WV) amendment (A003) Agreed to by voice vote. · Sponsored by Evan H. Jenkins

H.Amdt. 479Nov 8, 2017

An amendment numbered 2 printed in House Report 115-391 to allow FERC to examine the licenses of any project located in an area that was declared by the President to be a disaster area in 2017.

On agreeing to the Babin amendment (A002) Agreed to by voice vote. · Sponsored by Brian Babin

H.Amdt. 478Nov 8, 2017

An amendment numbered 1 printed in House Report 115-391 to require the U.S. Department of Interior consider the threat of invasive species when it makes decisions on hydropower licensing.

On agreeing to the Grothman amendment (A001) Agreed to by voice vote. · Sponsored by Glenn Grothman

Floor Debate

24 members

What members said about H.R. 3043 on the floor

15 Republicans9 Democrats
Bobby L. Rush
Rep. Bobby L. RushD-IL-1 · Nov 8, 2017

Mr. Chairman, I yield myself such time as I may consume. Mr. Chairman, I rise in strong opposition to H.R. 3043, the Hydropower Policy Modernization Act of 2017. Mr. Chairman, while Members on both…

James P. McGovern
Rep. James P. McGovernD-MA-2 · Nov 7, 2017

Mr. Speaker, I thank the gentleman from Alabama (Mr. Byrne) for yielding me the customary 30 minutes, and I yield myself such time as I may consume. (Mr. McGOVERN asked and was given permission to…

Steny H. Hoyer
Rep. Steny H. HoyerD-MD-5 · Nov 3, 2017

Mr. Speaker, I yield to the gentleman from California (Mr. McCarthy), the majority leader, for the purpose of inquiring about the schedule for the week to come. (Mr. McCARTHY asked and was given…

Bradley Byrne
Rep. Bradley ByrneR-AL-1 · Nov 7, 2017

Mr. Speaker, by direction of the Committee on Rules, I call up House Resolution 607 and ask for its immediate consideration. Mr. Speaker, for the purpose of debate only, I yield the customary 30…

Kevin McCarthy
Rep. Kevin McCarthyR-CA-23 · Nov 3, 2017

Mr. Speaker, I thank the gentleman for yielding. Mr. Speaker, on Monday, the House will meet at noon for morning hour and 2 p.m. for legislative business. Votes will be postponed until 6:30. On…

Show 8 more
Fred Upton
Rep. Fred UptonR-MI-6 · Nov 8, 2017

Mr. Speaker, I ask unanimous consent that all Members may have 5 legislative days to revise and extend their remarks and include in the Record extraneous material on H.R. 3043. Mr. Chairman, I yield…

Greg Walden
Rep. Greg WaldenR-OR-2 · Nov 8, 2017

Mr. Chairman, I want to draw attention, first of all, to page 17, line 23, of the bill because we have heard from those who oppose it that somehow this could adversely undermine the Federal Water…

Frank Pallone, Jr.
Rep. Frank Pallone, Jr.D-NJ-6 · Nov 8, 2017

Mr. Chair, I thank Mr. Rush, our ranking member of the subcommittee, for yielding. Mr. Chair, I rise in strong opposition to H.R. 3043. I support hydropower. It can deliver low-carbon, affordable…

Keith Ellison
Rep. Keith EllisonD-MN-5 · Nov 7, 2017

Mr. Speaker, I urge Members to vote ``no'' on the Republican effort to roll back the joint-employer rule that the Obama administration promulgated. This joint-employer rule is an attack on workers,…

H. Morgan Griffith
Rep. H. Morgan GriffithR-VA-9 · Nov 8, 2017

Mr. Chairman, hydropower is an essential component of an all-of-the-above energy strategy. We have a tremendous opportunity to expand renewable hydropower production. However, without some…

Glenn Grothman
Rep. Glenn GrothmanR-WI-6 · Nov 8, 2017

Mr. Chair, as the designee of my friend and colleague, Mr. Pocan, I have an amendment at the desk. Mr. Chair, first of all, I would like to thank the chair and ranking member for their collaborative…

Paul Tonko
Rep. Paul TonkoD-NY-20 · Nov 8, 2017

Mr. Chairman, I thank the ranking member of our subcommittee, the gentleman from Illinois, for his leadership and hard work on the subcommittee and for yielding me this time. Mr. Chairman, I want to…

Tom Cole
Rep. Tom ColeR-OK-4 · Nov 8, 2017

Mr. Chair, I rise today in opposition to H.R. 3043, the Hydropower Policy Modernization Act of 2017. However, I would like to point out the positive outcomes this bill would provide to the Hydropower…

Show 11 more
Lucille Roybal-Allard
Rep. Lucille Roybal-AllardD-CA-40 · Nov 13, 2017

Mr. Speaker, on November 6th, 7th, 8th, and 9th, I was ill, so I was not present for the Roll Call votes held on those days. Had I been present, I would have voted: ``Aye'' on Roll Call 607, on the…

Dan Newhouse
Rep. Dan NewhouseR-WA-4 · Nov 7, 2017

Mr. Speaker, first, I want to thank my friend, the gentleman from Alabama, for letting me participate in this very important debate today. Mr. Speaker, I rise in support of the rule, but specifically…

Brian Babin
Rep. Brian BabinR-TX-36 · Nov 8, 2017

Mr. Chairman, I have an amendment at the desk. Mr. Chairman, when a disaster like Hurricane Harvey strikes, the most important job we have is to assist those in harm's way. From the Texas National…

Clay Higgins
Rep. Clay HigginsR-LA-3 · Nov 8, 2017

Mr. Chairman, I rise today in support of amendment No. 2 to the Hydropower Policy Modernization Act of 2017, offered by my friend, Representative Babin of Texas. My colleague's amendment, of which I…

Paul A. Gosar
Rep. Paul A. GosarR-AZ-4 · Nov 8, 2017

Mr. Chairman, I rise today in strong support of H.R. 3043 from Representative McMorris Rodgers, the Hydropower Policy Modernization Act of 2017. For centuries, Western States have fought over scarce…

Doug Lamborn
Rep. Doug LambornR-CO-5 · Nov 8, 2017

Mr. Chairman, I rise today in support of H.R. 3043, the Hydropower Policy Modernization Act of 2017, sponsored by the gentlewoman from the State of Washington (Mrs. McMorris Rodgers). This bill…

Jeff Denham
Rep. Jeff DenhamR-CA-10 · Nov 8, 2017

Mr. Chair, I rise in support of H.R. 3043, the Hydropower Modernization Act of 2017. In my area of California's Central Valley, we have the Turlock and Modesto Irrigation Districts. They have been…

Evan H. Jenkins
Rep. Evan H. JenkinsR-WV-3 · Nov 8, 2017

Mr. Chairman, I have an amendment at the desk. Mr. Chairman, my amendment is very straightforward. It supports the mission of the underlying bill to responsibly increase opportunities for hydropower…

Raul Ruiz
Rep. Raul RuizD-CA-36 · Nov 8, 2017

Mr. Chairman, I rise in strong opposition to H.R. 3043, the Hydropower Policy Modernization Act, which undercuts Federal-Tribal treaty and trust obligations. In fact, parts of this bill specifically…

Ralph Norman
Rep. Ralph NormanR-SC-5 · Nov 7, 2017

Mr. Speaker, I rise today in adamant support of the rule and, in particular, of H.R. 3441, the Save Local Business Act. Let me say for my good friend from Massachusetts, you know, the amendments that…

Eddie Bernice Johnson
Rep. Eddie Bernice JohnsonD-TX-30 · Nov 9, 2017

Mr. Speaker, on Tuesday, November 6, 2017, I requested and was granted a leave of absence for the rest of the week due to the death of my sister. For the information of our colleagues and my…

Bill Text

4 versions available

Reading Mode
Latest
Referred in SenateIssued November 9, 2017

IIB

115th CONGRESS

1st Session

H. R. 3043

IN THE SENATE OF THE UNITED STATES

November 9, 2017

Received; read twice and referred to the Committee on Energy and Natural Resources

AN ACT

To modernize hydropower policy, and for other purposes.

1.

Short title

This Act may be cited as the Hydropower Policy Modernization Act of 2017.

2.

Hydropower regulatory improvements

(a)

Sense of Congress on the use of hydropower renewable resources

It is the sense of Congress that—

(1)

hydropower is a renewable resource for purposes of all Federal programs and is an essential source of energy in the United States; and

(2)

the United States should increase substantially the capacity and generation of clean, renewable hydropower that would improve environmental quality in the United States.

(b)

Modifying the definition of renewable energy to include hydropower

Section 203 of the Energy Policy Act of 2005 (42 U.S.C. 15852) is amended—

(1)

in subsection (a), by striking the following amounts and all that follows through paragraph (3) and inserting not less than 15 percent in fiscal year 2017 and each fiscal year thereafter shall be renewable energy.; and

(2)

in subsection (b), by striking paragraph (2) and inserting the following:

(2)

Renewable energy

The term renewable energy means electric energy generated from solar, wind, biomass, landfill gas, ocean (including tidal, wave, current, and thermal), geothermal, or municipal solid waste, or from a hydropower project.

.

(c)

Preliminary permits

Section 5 of the Federal Power Act (16 U.S.C. 798) is amended—

(1)

in subsection (a), by striking three and inserting 4; and

(2)

by amending subsection (b) to read as follows:

(b)

The Commission may—

(1)

extend the period of a preliminary permit once for not more than 4 additional years beyond the 4 years permitted by subsection (a) if the Commission finds that the permittee has carried out activities under such permit in good faith and with reasonable diligence; and

(2)

if the period of a preliminary permit is extended under paragraph (1), extend the period of such preliminary permit once for not more than 4 additional years beyond the extension period granted under paragraph (1), if the Commission determines that there are extraordinary circumstances that warrant such additional extension.

.

(d)

Time limit for construction of project works

Section 13 of the Federal Power Act (16 U.S.C. 806) is amended in the second sentence by striking once but not longer than two additional years and inserting for not more than 8 additional years,.

(e)

License term

Section 15(e) of the Federal Power Act (16 U.S.C. 808(e)) is amended—

(1)

by striking (e) Except and inserting the following:

(e)

License term on relicensing

(1)

In general

Except

; and

(2)

by adding at the end the following:

(2)

Consideration

In determining the term of a license under paragraph (1), the Commission shall consider, among other things, project-related investments to be made by the licensee under a new license issued under this section, as well as project-related investments made by a licencee over the term of the existing license (including any terms under annual licenses). In considering such investments, the Commission shall give the same weight to—

(A)

investments to be made by the licensee to implement a new license issued under this section, including—

(i)

investments in redevelopment, new construction, new capacity, efficiency, modernization, rehabilitation, and safety improvements; and

(ii)

investments in environmental, recreation, and other protection, mitigation, or enhancement measures that will be required or authorized by the license; and

(B)

investments made by the licensee over the term of the existing license (including any terms under annual licenses), beyond those required by the existing license when issued, that—

(i)

resulted in, during the term of the existing license—

(I)

redevelopment, new construction, new capacity, efficiency, modernization, rehabilitation, or safety improvements; or

(II)

environmental, recreation, or other protection, mitigation, or enhancement measures; and

(ii)

did not result in the extension of the term of the existing license by the Commission.

.

(f)

Alternative conditions and prescriptions

Section 33 of the Federal Power Act (16 U.S.C. 823d) is amended—

(1)

in subsection (a)—

(A)

in paragraph (1), by striking deems and inserting determines;

(B)

in paragraph (2)(B), in the matter preceding clause (i), by inserting determined to be necessary before by the Secretary;

(C)

by striking paragraph (4); and

(D)

by striking paragraph (5);

(2)

in subsection (b)—

(A)

by striking paragraph (4); and

(B)

by striking paragraph (5); and

(3)

by adding at the end the following:

(c)

Further conditions

This section applies to any further conditions or prescriptions proposed or imposed pursuant to section 4(e), 6, or 18.

.

3.

Hydropower licensing and process improvements

(a)

Hydropower licensing and process improvements

Part I of the Federal Power Act (16 U.S.C. 792 et seq.) is amended by adding at the end the following:

34.

Hydropower licensing and process improvements

(a)

Definition

In this section, the term Federal authorization—

(1)

means any authorization required under Federal law with respect to an application for a license under this part; and

(2)

includes any permits, special use authorizations, certifications, opinions, or other approvals as may be required under Federal law to approve or implement the license under this part.

(b)

Designation as lead agency

(1)

In general

The Commission shall act as the lead agency for the purposes of coordinating all applicable Federal authorizations and for the purposes of complying with the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).

(2)

Other agencies and Indian tribes

(A)

In general

Each Federal, State, and local government agency and Indian tribe considering an aspect of an application for Federal authorization shall coordinate with the Commission and comply with the deadline established in the schedule developed for the license under this part in accordance with the rule issued by the Commission under subsection (c).

(B)

Identification

The Commission shall identify, as early as practicable after it is notified by the applicant for a license under this part, any Federal or State agency, local government, or Indian tribe that may consider an aspect of an application for a Federal authorization.

(C)

Notification

(i)

In general

The Commission shall notify any agency and Indian tribe identified under subparagraph (B) of the opportunity to participate in the process of reviewing an aspect of an application for a Federal authorization.

(ii)

Deadline

Each agency and Indian tribe receiving a notice under clause (i) shall submit a response acknowledging receipt of the notice to the Commission within 30 days of receipt of such notice and request.

(D)

Issue identification and resolution

(i)

Identification of issues

Federal, State, and local government agencies and Indian tribes that may consider an aspect of an application for Federal authorization shall identify, as early as possible, and share with the Commission and the applicant, any issues of concern identified during the pendency of the Commission’s action under this part relating to any Federal authorization that may delay or prevent the granting of such authorization, including any issues that may prevent the agency or Indian tribe from meeting the schedule established for the license under this part in accordance with the rule issued by the Commission under subsection (c).

(ii)

Issue resolution

The Commission may forward any issue of concern identified under clause (i) to the heads of the relevant State and Federal agencies (including, in the case of an issue of concern identified by a State or local government agency or Indian tribe, the Federal agency overseeing the delegated authority, or the Secretary of the Interior with regard to an issue of concern identified by an Indian tribe, as applicable) for resolution. If the Commission forwards an issue of concern to the head of a relevant agency, the Commission and the relevant agency shall enter into a memorandum of understanding to facilitate interagency coordination and resolution of such issues of concern, as appropriate.

(c)

Schedule

(1)

Commission rulemaking to establish process to set schedule

Not later than 180 days after the date of enactment of this section the Commission shall, in consultation with the appropriate Federal agencies, issue a rule, after providing for notice and public comment, establishing a process for setting a schedule following the filing of an application under this part for a license for the review and disposition of each Federal authorization.

(2)

Elements of scheduling rule

In issuing a rule under this subsection, the Commission shall ensure that the schedule for each Federal authorization—

(A)

includes deadlines for actions by—

(i)

any Federal or State agency, local government, or Indian tribe that may consider an aspect of an application for the Federal authorization;

(ii)

the applicant;

(iii)

the Commission; and

(iv)

other participants in any applicable proceeding;

(B)

is developed in consultation with the applicant and any agency and Indian tribe that submits a response under subsection (b)(2)(C)(ii);

(C)

provides an opportunity for any Federal or State agency, local government, or Indian tribe that may consider an aspect of an application for the applicable Federal authorization to identify and resolve issues of concern, as provided in subsection (b)(2)(D);

(D)

complies with applicable schedules established under Federal and State law;

(E)

ensures expeditious completion of all proceedings required under Federal and State law, to the extent practicable; and

(F)

facilitates completion of Federal and State agency studies, reviews, and any other procedures required prior to, or concurrent with, the preparation of the Commission’s environmental document required under the National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.).

(d)

Transmission of final schedule

(1)

In General

For each application for a license under this part, the Commission shall establish a schedule in accordance with the rule issued by the Commission under subsection (c). The Commission shall publicly notice and transmit the final schedule to the applicant and each agency and Indian tribe identified under subsection (b)(2)(B).

(2)

Response

Each agency and Indian tribe receiving a schedule under this subsection shall acknowledge receipt of such schedule in writing to the Commission within 30 days.

(e)

Adherence to schedule

All applicants, other licensing participants, and agencies and Indian tribes considering an aspect of an application for a Federal authorization shall meet the deadlines set forth in the schedule established pursuant to subsection (d)(1).

(f)

Application processing

The Commission, Federal, State, and local government agencies, and Indian tribes may allow an applicant seeking a Federal authorization to fund a third-party contractor selected by such an agency or tribe to assist in reviewing the application. All costs of an agency or tribe incurred pursuant to direct funding by the applicant, including all costs associated with the third party contractor, shall not be considered costs of the United States for the administration of this part under section 10(e).

(g)

Commission recommendation on scope of environmental review

For the purposes of coordinating Federal authorizations for each license under this part, the Commission shall consult with and make a recommendation to agencies and Indian tribes receiving a schedule under subsection (d) on the scope of the environmental review for all Federal authorizations for such license. Each Federal and State agency and Indian tribe shall give due consideration and may give deference to the Commission’s recommendations, to the extent appropriate under Federal law.

(h)

Extension of deadline

(1)

Application

A Federal, State, or local government agency or Indian tribe that is unable to complete its disposition of a Federal authorization by the deadline set forth in the schedule established under subsection (d)(1) shall, not later than 30 days prior to such deadline, file for an extension with the Commission.

(2)

Extension

The Commission shall only grant an extension filed for under paragraph (1) if the agency or Indian tribe demonstrates, based on the record maintained under subsection (i), that complying with the schedule established under subsection (d)(1) would prevent the agency or tribe from complying with applicable Federal or State law. If the Commission grants the extension, the Commission shall set a reasonable schedule and deadline, that is not later than 90 days after the deadline set forth in the schedule established under subsection (d)(1), for the agency or tribe to complete its disposition of the Federal authorization.

(i)

Consolidated record

The Commission shall, with the cooperation of Federal, State, and local government agencies and Indian tribes, maintain a complete consolidated record of all decisions made or actions taken by the Commission or by a Federal administrative agency or officer (or State or local government agency or officer or Indian tribe acting under delegated Federal authority) with respect to any Federal authorization. Such record shall constitute the record for judicial review under section 313(b).

(j)

Submission of license recommendations, conditions, and prescriptions

(1)

Submission of recommendations

Any Federal or State agency that is providing recommendations with respect to a license proceeding under this part shall submit to the Commission for inclusion in the consolidated record relating to the license proceeding maintained under subsection (i)—

(A)

the recommendations;

(B)

the rationale for the recommendations; and

(C)

any supporting materials relating to the recommendations.

(2)

Written statement

In a case in which a Federal agency is making a determination with respect to a covered measure (as defined in section 35(a)), the head of the Federal agency shall submit to the Commission for inclusion in the consolidated record, in addition to the information required under paragraph (1), a written statement demonstrating that the Federal agency gave equal consideration to the effects of the covered measure on—

(A)

energy supply, distribution, cost, and use;

(B)

flood control;

(C)

navigation;

(D)

water supply; and

(E)

air quality and the preservation of other aspects of environmental quality.

(3)

Information from other agencies

In preparing a written statement under paragraph (2), the head of a Federal agency may make use of information produced or made available by other agencies with relevant expertise in the factors described in subparagraphs (A) through (E) of that paragraph.

(k)

Delegation

A Secretary may delegate the authority to determine a condition to be necessary under section 4(e), or to prescribe a fishway under section 18, to an officer of the applicable department based, in part, on the ability of the officer to evaluate the broad effects of such condition or prescription on—

(1)

the applicable project; and

(2)

the factors described in subparagraphs (A) through (E) of subsection (j)(2).

(l)

No effect on other laws

Nothing in this section shall be construed to affect any requirement of the Federal Water Pollution Control Act, the Fish and Wildlife Coordination Act, the Endangered Species Act of 1973, section 14 of the Act of March 3, 1899 (commonly known as the Rivers and Harbors Appropriation Act of 1899), and those provisions in subtitle III of title 54, United States Code commonly known as the National Historic Preservation Act, with respect to an application for a license under this part.

35.

Trial-type hearings

(a)

Definition of covered measure

In this section, the term covered measure means—

(1)

a condition determined to be necessary under section 4(e), including an alternative condition proposed under section 33(a);

(2)

fishways prescribed under section 18, including an alternative prescription proposed under section 33(b); or

(3)

any action by the Secretary to exercise reserved authority under the license to prescribe, submit, or revise any condition to a license under the first proviso of section 4(e) or fishway prescribed under section 18.

(b)

Authorization of trial-type hearing

An applicant for a license under this part (including an applicant for a license under section 15) and any party to a license proceeding shall be entitled to a determination on the record, after opportunity for a trial-type hearing of not more than 120 days, on any disputed issues of material fact with respect to an applicable covered measure.

(c)

Deadline for request

A request for a trial-type hearing under this section shall be submitted not later than 60 days after the date on which, as applicable—

(1)

the Secretary determines the condition to be necessary under section 4(e) or prescribes the fishway under section 18; or

(2)

the Secretary exercises reserved authority under the license to prescribe, submit, or revise any condition to a license under the first proviso of section 4(e) or fishway prescribed under section 18, as appropriate.

(d)

No requirement to exhaust

By electing not to request a trial-type hearing under subsection (c), a license applicant and any other party to a license proceeding shall not be considered to have waived the right of the applicant or other party to raise any issue of fact or law in a non-trial-type proceeding, but no issue may be raised for the first time on rehearing or judicial review of the license decision of the Commission.

(e)

Administrative Law Judge

(1)

In general

All disputed issues of material fact raised by a party in a request for a trial-type hearing submitted under subsection (c) shall be determined in a single trial-type hearing to be conducted by an Administrative Law Judge within the Office of Administrative Law Judges and Dispute Resolution of the Commission, in accordance with the Commission rules of practice and procedure under part 385 of title 18, Code of Federal Regulations (or successor regulations), and within the timeframe established by the Commission for each license proceeding (including a proceeding for a license under section 15) under section 34(d).

(2)

Requirement

The trial-type hearing shall include the opportunity—

(A)

to undertake discovery; and

(B)

to cross-examine witnesses, as applicable.

(f)

Stay

The Administrative Law Judge may impose a stay of a trial-type hearing under this section for a period of not more than 120 days to facilitate settlement negotiations relating to resolving the disputed issues of material fact with respect to the covered measure.

(g)

Decision of the Administrative Law Judge

(1)

Contents

The decision of the Administrative Law Judge shall contain—

(A)

findings of fact on all disputed issues of material fact;

(B)

conclusions of law necessary to make the findings of fact, including rulings on materiality and the admissibility of evidence; and

(C)

reasons for the findings and conclusions.

(2)

Limitation

The decision of the Administrative Law Judge shall not contain conclusions as to whether—

(A)

any condition or prescription should be adopted, modified, or rejected; or

(B)

any alternative condition or prescription should be adopted, modified, or rejected.

(3)

Finality

A decision of an Administrative Law Judge under this section with respect to a disputed issue of material fact shall not be subject to further administrative review.

(4)

Service

The Administrative Law Judge shall serve the decision on each party to the hearing and forward the complete record of the hearing to the Commission and the Secretary that proposed the original condition or prescription.

(h)

Secretarial determination

(1)

In general

Not later than 60 days after the date on which the Administrative Law Judge issues the decision under subsection (g) and in accordance with any applicable schedule established by the Commission under section 34(d), the Secretary proposing a covered measure shall file with the Commission a final determination to adopt, modify, or withdraw any condition or prescription that was the subject of a hearing under this section, based on the decision of the Administrative Law Judge.

(2)

Record of determination

The final determination of the Secretary filed with the Commission shall identify the reasons for the decision and any considerations taken into account that were not part of, or were inconsistent with, the findings of the Administrative Law Judge and shall be included in the consolidated record maintained under section 34(i).

(i)

Resolution of matters

Notwithstanding sections 4(e) and 18, if the Commission finds that a final determination under (h)(1) of the Secretary is inconsistent with the purposes of this part or other applicable law, the Commission may enter into a memorandum of understanding with the Secretary to facilitate interagency coordination and resolve the matter.

(j)

Judicial review

The decision of the Administrative Law Judge and the record of determination of the Secretary shall be included in the record of the applicable licensing proceeding and subject to judicial review of the final licensing decision of the Commission under section 313(b).

36.

Licensing study improvements

(a)

In general

To facilitate the timely and efficient completion of the license proceedings under this part, the Commission shall, in consultation with applicable Federal and State agencies and interested members of the public—

(1)

compile current and accepted best practices in performing studies required in such license proceedings, including methodologies and the design of studies to assess the full range of environmental impacts of a project that reflect the most recent peer-reviewed science;

(2)

compile a comprehensive collection of studies and data accessible to the public that could be used to inform license proceedings under this part; and

(3)

encourage license applicants, agencies, and Indian tribes to develop and use, for the purpose of fostering timely and efficient consideration of license applications, a limited number of open-source methodologies and tools applicable across a wide array of projects, including water balance models and streamflow analyses.

(b)

Use of studies

To the extent practicable, the Commission and other Federal, State, and local government agencies and Indian tribes considering an aspect of an application for Federal authorization (as defined in section 34) shall use studies and data based on current, accepted science in support of their actions. Any participant in a proceeding with respect to such a Federal authorization shall demonstrate that a study requested by the participant is not duplicative of current, existing studies that are applicable to the project.

(c)

Intra-Watershed review

The Commission shall establish a program to develop comprehensive plans, at the request of project applicants, on a watershed-wide scale, in consultation with the applicants, appropriate Federal agencies, and affected States, local governments, and Indian tribes, in watersheds with respect to which there are more than one application for a project. Upon such a request, the Commission, in consultation with the applicants, such Federal agencies, and affected States, local governments, and Indian tribes, may conduct or commission watershed-wide environmental studies, with the participation of at least 2 applicants. Any study conducted under this subsection shall apply only to a project with respect to which the applicants participate.

37.

License amendment improvements

(a)

Qualifying project upgrades

(1)

In general

As provided in this section, the Commission may approve an application under this section for an amendment to a license issued under this part for a qualifying project upgrade.

(2)

Application

A licensee filing an application for an amendment to a project license, for which the licensee is seeking approval as a qualified project upgrade under this section, shall include in such application information sufficient to demonstrate that the proposed change to the project described in the application is a qualifying project upgrade.

(3)

Notice and initial determination on qualification

Not later than 30 days after receipt of an application under paragraph (2), the Commission, in consultation with other Federal agencies, States, and Indian tribes the Commission determines appropriate, shall publish in the Federal Register a notice containing—

(A)

notice of the application filed under paragraph (2);

(B)

an initial determination as to whether the proposed change to the project described in the application for a license amendment is a qualifying project upgrade; and

(C)

a request for public comment on the application and the initial determination.

(4)

Public comment and consultation

The Commission shall, for a period of 45 days beginning on the date of publication of a notice under paragraph (3)—

(A)

accept public comment regarding the application and whether the proposed license amendment is for a qualifying project upgrade; and

(B)

consult with each Federal, State, and local government agency and Indian tribe considering an aspect of an application for any authorization required under Federal law with respect to the proposed license amendment, as well as other interested agencies and Indian tribes.

(5)

Final determination on qualification

Not later than 15 days after the end of the public comment and consultation period under paragraph (4), the Commission shall publish in the Federal Register a final determination as to whether the proposed license amendment is for a qualifying project upgrade.

(6)

Federal authorizations

In establishing the schedule for a proposed license amendment for a qualifying project upgrade, the Commission shall require final disposition of all authorizations required under Federal law with respect to an application for such license amendment, other than final action by the Commission, by not later than 120 days after the date on which the Commission publishes a final determination under paragraph (5) that the proposed license amendment is for a qualifying project upgrade.

(7)

Commission action

Not later than 150 days after the date on which the Commission publishes a final determination under paragraph (5) that a proposed license amendment is for a qualifying project upgrade, the Commission shall take final action on the license amendment application.

(8)

License amendment conditions

Any condition or prescription included in or applicable to a license amendment for a qualifying project upgrade approved under this subsection, including any condition, prescription, or other requirement of a Federal authorization, shall be limited to those that are—

(A)

necessary to protect public safety; or

(B)

reasonable, economically feasible, and essential to prevent loss of or damage to, or to mitigate adverse effects on, fish and wildlife resources, water supply, and water quality that are directly caused by the construction and operation of the qualifying project upgrade, as compared to the environmental baseline existing at the time the Commission approves the application for the license amendment.

(9)

Rulemaking

Not later than 180 days after the date of enactment of this section, the Commission shall, after notice and opportunity for public comment, issue a rule to implement this subsection.

(10)

Definitions

For purposes of this subsection:

(A)

Qualifying project upgrade

The term qualifying project upgrade means a change to a project licensed under this part that meets the qualifying criteria, as determined by the Commission.

(B)

Qualifying criteria

The term qualifying criteria means, with respect to a project licensed under this part, a change to the project that—

(i)

if carried out, would be unlikely to adversely affect any species listed as threatened or endangered under the Endangered Species Act of 1973 or result in the destruction or adverse modification of critical habitat, as determined in consultation with the Secretary of the Interior or Secretary of Commerce, as appropriate, in accordance with section 7 of the Endangered Species Act of 1973;

(ii)

is consistent with any applicable comprehensive plan under section 10(a)(2);

(iii)

includes only changes to project lands, waters, or operations that, in the judgment of the Commission, would result in only insignificant or minimal cumulative adverse environmental effects;

(iv)

would be unlikely to adversely affect water quality or water supply; and

(v)

proposes to implement—

(I)

capacity increases, efficiency improvements, or other enhancements to hydropower generation at the licensed project;

(II)

environmental protection, mitigation, or enhancement measures to benefit fish and wildlife resources or other natural and cultural resources; or

(III)

improvements to public recreation at the licensed project.

(b)

Amendment approval processes

(1)

Rule

Not later than 1 year after the date of enactment of this section, the Commission shall, after notice and opportunity for public comment, issue a rule establishing new standards and procedures for license amendment applications under this part. In issuing such rule, the Commission shall seek to develop the most efficient and expedient process, consultation, and review requirements, commensurate with the scope of different categories of proposed license amendments. Such rule shall account for differences in environmental effects across a wide range of categories of license amendment applications.

(2)

Capacity

In issuing a rule under this subsection, the Commission shall take into consideration that a change in generating or hydraulic capacity may indicate the potential environmental effects of a proposed license amendment but is not determinative of such effects.

(3)

Process options

In issuing a rule under this subsection, the Commission shall take into consideration the range of process options available under the Commission’s regulations for license applications and adapt such options to amendment applications, where appropriate.

.

4.

Technical and conforming amendments

(a)

Licenses

Section 4(e) of the Federal Power Act (16 U.S.C. 797(e)) is amended—

(1)

by striking adequate protection and utilization of such reservation and all that follows through That no license affecting the navigable capacity and inserting adequate protection and utilization of such reservation: Provided further, That no license affecting the navigable capacity; and

(2)

by striking deem and inserting determine.

(b)

Operation of navigation facilities

Section 18 of the Federal Power Act (16 U.S.C. 811) is amended by striking the second, third, and fourth sentences.

5.

Consideration of invasive species

Section 18 of the Federal Power Act (16 U.S.C. 811) is amended by inserting after the Secretary of Commerce. the following: In prescribing a fishway, the Secretary of Commerce or the Secretary of the Interior, as appropriate, shall consider the threat of invasive species..

6.

Examination of licenses for projects located in disaster areas

Not later than one year after the date of enactment of this Act, the Federal Energy Regulatory Commission may examine the license issued by the Commission under part I of the Federal Power Act for any project that is located in an area that was declared by the President to be a disaster area in 2017.

7.

Studies for non-federal hydropower

Notwithstanding any other provision of law, if the Federal Energy Regulatory Commission has in place a memorandum of understanding with another Federal agency for non-federal hydropower with respect to a project licensed under part I of the Federal Power Act (regardless of explicit Congressional authorization for such non-federal hydropower), the other Federal agency may fully study and review the potential expansion of such non-federal hydropower at the project, including a review of seasonal pool levels and slowing flood releases.

Passed the House of Representatives November 8, 2017.